ACTIVITY TITLE
Maroc - Programme intégré éolien, hydraulique et électrification rurale
Morocco - Integrated Wind/Hydro and Rural Electrification Programme
Reported by
African Development Bank XM-DAC-46002 Multilateral
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Sub-national: Multi-first-level administrative areas 5 Multilateral (inflows) 2 Standard loan 421 ODA 10 Untied 1
DOCUMENTS ( 35 )
Appraisal Report APPLICATION/PDF EN Pre- and post-project impact appraisal Objectives / Purpose of activity Objectives / Purpose of activity Intended ultimate beneficiaries Conditions Budget Results, outcomes and outputs Appraisal Report APPLICATION/PDF FR Pre- and post-project impact appraisal Objectives / Purpose of activity Objectives / Purpose of activity Intended ultimate beneficiaries Conditions Budget Results, outcomes and outputs Environmental Study APPLICATION/PDF EN Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Environmental Study APPLICATION/PDF FR Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Evaluation Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Evaluation Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Evaluation Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Project Completion Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Project Completion Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Evaluation Report APPLICATION/PDF FR Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Evaluation Report APPLICATION/PDF FR Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Project Completion Report APPLICATION/PDF FR Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/PDF FR Summary information about contract Contract Contract APPLICATION/PDF FR Summary information about contract Contract Contract APPLICATION/PDF FR Summary information about contract Contract Contract APPLICATION/PDF FR Summary information about contract Contract Contract APPLICATION/PDF FR Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL FR Summary information about contract Contract General Procurement Notice APPLICATION/PDF FR Tender Invitation for Bids APPLICATION/PDF FR Tender Invitation for Bids APPLICATION/PDF FR Tender Invitation for Bids APPLICATION/PDF FR Tender Invitation for Bids APPLICATION/PDF FR Tender Invitation for Bids APPLICATION/PDF FR Tender Activity TEXT/HTML FR Activity web page Activity TEXT/HTML FR Activity web page
Planned start date 2012-06-13
Planned end date 2023-12-31
Actual start date 2012-12-19
Actual end date 2024-06-12
activity status: Finalisation
Physical activity is complete or the final disbursement has been made, but the activity remains open pending financial sign off or M&E
WHO'S INVOLVED ( 5 )
PARTICIPATING ORG REFERENCE ROLE TYPE
African Development Bank
Funding Multilateral
Clean Technology Fund
Funding Multilateral
European Investment Bank (EIB)
Funding Multilateral
National Water Office of Morocco (ONE)
Funding Multilateral
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
Implementing Government
Target Groups
De manière spécifique, le programme bénéficiera au Gouvernement, à l’ONE (Office national de l'électricité), aux populations en zones rurale et urbaine du Maroc et contribuera à la réduction de la croissance des émissions de gaz à effet de serre. Le programme concerne quatre sites pour les ouvrages de production et stockage d’énergie et vingt-cinq provinces pour l’électrification rurale dont certaines sont d’accès difficile. Environ 86 000 foyers vont bénéficier de l’accès à l’électricité. Le programme servira, notamment, d’appui financier pour des initiatives de développement local à travers les ressources générées par des activités telles que l’acquisition de terrains.
Specifically, the program will benefit the Government, ONE (National Electricity Board), rural and urban populations in Morocco, and contribute to reducing the growth of greenhouse gas emissions. The program covers four sites for energy production and storage facilities, and twenty-five provinces for rural electrification, some of which are difficult to access. Around 6,000 households will benefit from access to electricity. The program will be used to provide financial support for local development initiatives through the resources generated by activities such as land acquisition.
General
Le Programme intégré éolien, hydraulique et électrification rurale s’inscrit dans la vision stratégique du Maroc d’améliorer sa sécurité énergétique, d’assurer l’accès à l’énergie aux zones rurales, et d’augmenter la part des énergies renouvelables et propres, atténuant ainsi les effets de sa production d’énergie électrique sur le changement climatique. Il est estimé que le programme aidera à empêcher l'émission de 65 millions de tonnes de CO2 sur toute sa durée de vie. Il permettra une plus grande participation du secteur privé dans la production indépendante d’énergie éolienne, et enfin, contribuera à l’amélioration de la balance commerciale du Maroc puisque 97% des sources d’énergie primaire proviennent actuellement de l’importation. Le programme comprend trois composantes. La composante relative à la production d’électricité d’origine hydraulique et éolienne est appelée « EOLIEN » tandis que celle relative à l’électrification rurale est appelée « PERG ». La troisième composante a trait à la gestion du programme. La composante « EOLIEN » comporte la construction de 3 parcs éoliens (dont 2 concernés par le financement de la Banque) d’une capacité totale de 550 MW situés au Nord du Maroc ; un ensemble comprenant une Station de transfert d’énergie par pompage (STEP) et un complexe hydroélectrique ayant une capacité totale de 520 MW. Elle comporte la construction des lignes de transport d’énergie pour l’interconnexion de ces ouvrages de production d’électricité au réseau national et l’assistance technique. Les 2 parcs éoliens seront construits sur la période 2012-2017.
The Integrated Wind/Hydro and Rural Electrification Programme is part of of Morocco’s strategic vision to improve its energy security, ensure access to energy in rural areas, and increase the share of renewable and clean energies, thus mitigating the effects of electrical power generation on climate change. It is estimated that the program will help prevent the emission of 65 million tonnes of CO2 over its entire lifetime. The program will allow for greater private sector participation in independent wind energy production, and finally will improve Morocco’s trade balance since 97% of primary energy sources currently come from imports. The project has three components. The hydroelectric and wind power component is called "WIND" while the rural electrification is called "PERG". The third component relates to the management of the program. The component "WIND" includes the construction of 3 wind farms (2 of which are financed by the Bank) with a total capacity of 550 MW located in northern Morocco; a set including a station of energy transfer by Pumped Power Transfer Station Project (STEP) and a hydropower complex with a total capacity of 520 MW. It involves the construction of transmission lines for the interconnection of these power generation facilities to the national grid and technical assistance. The 2 wind farms will be built over the 2012-2017 period.
Objectives
L’objectif du programme est de contribuer à la sécurité des approvisionnements énergétiques à travers: i) la diversification des ressources énergétiques; ii) à la réduction des émissions de gaz à effet de serre (CO2) et à l’harmonisation des taux d’accès rural et urbain.
The programme objective is to contribute to energy supply security through: i) the diversification of energy sources; ii) a reduction in greenhouse gas emissions (CO2) and the harmonization of rural and urban access rates.
recipient country ( 1 )
MoroccoMA
100
LOCATION ( 3 )
NAME DESCRIPTION POSITION CLASS REACH EXACTNESS
Chefchaouene
ID 2553455 (Global Admininistrative Unit Layers)
TYPE seat of a second-order administrative division PPLA2
35.1688 -5.2636 Populated Place Approximate
Guercif
ID 6547086 (Geonames)
TYPE populated place PPL
34.2251 -3.35235 Populated Place Approximate
Rabat
ID 2538475 (Geonames)
TYPE capital of a political entity PPLC
34.0133 -6.83255 Populated Place Approximate
country budget items ( 1 )
IATI Withdrawn ( 1 )
The budget identifier reported uses IATI budget identifier categories
3.6.1
100
sector ( 1 )
OECD DAC CRS 5 digit1( 1 )
The sector reported corresponds to an OECD DAC CRS 5-digit purpose code http://reference.iatistandard.org/codelists/Sector/
Energy sector policy, planning and administration23111
100
GLOSSARY
Energy sector policy, planning and administrationNo description provided
Financial Overview
Outgoing Commitment ( 2 )
Disbursement ( 61 )
Interest Payment ( 22 )
Loan Repayment ( 21 )
Budget ( 45 )
Outgoing Commitment
Disbursement
Interest Payment
Loan Repayment
Budget
Budget ( 45 )
START END TYPE STATUS VALUE
2012-12-19 2013-03-19 Original 6,206,946.024889
XDR
2013-03-19 2013-06-19 Original 6,206,946.024889
XDR
2013-06-19 2013-09-19 Original 6,206,946.024889
XDR
2013-09-19 2013-12-19 Original 6,206,946.024889
XDR
2013-12-19 2014-03-19 Original 6,206,946.024889
XDR
2014-03-19 2014-06-19 Original 6,206,946.024889
XDR
2014-06-19 2014-09-19 Original 6,206,946.024889
XDR
2014-09-19 2014-12-19 Original 6,206,946.024889
XDR
2014-12-19 2015-03-19 Original 6,206,946.024889
XDR
2015-03-19 2015-06-19 Original 6,206,946.024889
XDR
2015-06-19 2015-09-19 Original 6,206,946.024889
XDR
2015-09-19 2015-12-19 Original 6,206,946.024889
XDR
2015-12-19 2016-03-19 Original 6,206,946.024889
XDR
2016-03-19 2016-06-19 Original 6,206,946.024889
XDR
2016-06-19 2016-09-19 Original 6,206,946.024889
XDR
2016-09-19 2016-12-19 Original 6,206,946.024889
XDR
2016-12-19 2017-03-19 Original 6,206,946.024889
XDR
2017-03-19 2017-06-19 Original 6,206,946.024889
XDR
2017-06-19 2017-09-19 Original 6,206,946.024889
XDR
2017-09-19 2017-12-19 Original 6,206,946.024889
XDR
2017-12-19 2018-03-19 Original 6,206,946.024889
XDR
2018-03-19 2018-06-19 Original 6,206,946.024889
XDR
2018-06-19 2018-09-19 Original 6,206,946.024889
XDR
2018-09-19 2018-12-19 Original 6,206,946.024889
XDR
2018-12-19 2019-03-19 Original 6,206,946.024889
XDR
2019-03-19 2019-06-19 Original 6,206,946.024889
XDR
2019-06-19 2019-09-19 Original 6,206,946.024889
XDR
2019-09-19 2019-12-19 Original 6,206,946.024889
XDR
2019-12-19 2020-03-19 Original 6,206,946.024889
XDR
2020-03-19 2020-06-19 Original 6,206,946.024889
XDR
2020-06-19 2020-09-19 Original 6,206,946.024889
XDR
2020-09-19 2020-12-19 Original 6,206,946.024889
XDR
2020-12-19 2021-03-19 Original 6,206,946.024889
XDR
2021-03-19 2021-06-19 Original 6,206,946.024889
XDR
2021-06-19 2021-09-19 Original 6,206,946.024889
XDR
2021-09-19 2021-12-19 Original 6,206,946.024889
XDR
2021-12-19 2022-03-19 Original 6,206,946.024889
XDR
2022-03-19 2022-06-19 Original 6,206,946.024889
XDR
2022-06-19 2022-09-19 Original 6,206,946.024889
XDR
2022-09-19 2022-12-19 Original 6,206,946.024889
XDR
2022-12-19 2023-03-19 Original 6,206,946.024889
XDR
2023-03-19 2023-06-19 Original 6,206,946.024889
XDR
2023-06-19 2023-09-19 Original 6,206,946.024889
XDR
2023-09-19 2023-12-19 Original 6,206,946.024889
XDR
2023-12-19 2024-06-12 Original 6,206,946.024889
XDR
Budget
Transactions ( 106 )
Outgoing Commitment ( 2 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2012-12-19
REF 2000130018181
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
109,597,714.85
XDR
2012-12-19
REF 5560130000801
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
44,235,065.14
XDR
Outgoing Commitment
Disbursement ( 61 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2018-05-31
Total Disbursement in May of 2018
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
15,104,160.45
XDR
2019-05-31
Total Disbursement in May of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,389,696.04
XDR
2019-06-30
Total Disbursement in June of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
455,502.73
XDR
2019-07-31
Total Disbursement in July of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
499,639.15
XDR
2019-09-30
Total Disbursement in September of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,264,695.13
XDR
2019-10-31
Total Disbursement in October of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
828,801.98
XDR
2020-01-31
Total Disbursement in January of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
785,923.9
XDR
2020-02-29
Total Disbursement in February of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,304,034.66
XDR
2020-03-31
Total Disbursement in March of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
393,917.51
XDR
2020-04-30
Total Disbursement in April of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,307,143.13
XDR
2020-05-15
Total Disbursement in May of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,492,415
XDR
2020-05-31
Total Disbursement in May of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
5,707,299.5
XDR
2020-06-15
Total Disbursement in June of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
217,715.23
XDR
2020-06-30
Total Disbursement in June of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,160,931.51
XDR
2020-07-31
Total Disbursement in July of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,350,543.85
XDR
2020-08-31
Total Disbursement in August of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,040,883.42
XDR
2020-11-15
Total Disbursement in November of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,705,927.85
XDR
2020-11-30
Total Disbursement in November of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,763,072.62
XDR
2020-12-31
Total Disbursement in December of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
290,431.38
XDR
2021-01-31
Total Disbursement in January of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,248,852.09
XDR
2021-02-28
Total Disbursement in February of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
20,832.88
XDR
2021-03-31
Total Disbursement in March of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
821,341.29
XDR
2021-04-15
Total Disbursement in April of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
7,752,105.29
XDR
2021-04-30
Total Disbursement in April of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
9,270,571.48
XDR
2021-05-31
Total Disbursement in May of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
752,070.88
XDR
2021-06-15
Total Disbursement in June of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
3,938,681.34
XDR
2021-06-30
Total Disbursement in June of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
630,804.52
XDR
2021-07-15
Total Disbursement in July of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
7,317,622.97
XDR
2021-07-31
Total Disbursement in July of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
821,673.01
XDR
2021-08-15
Total Disbursement in August of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
45,335.1
XDR
2021-08-31
Total Disbursement in August of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,302,603.6
XDR
2021-09-30
Total Disbursement in September of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
862,970.5
XDR
2021-10-15
Total Disbursement in October of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
981,005.85
XDR
2021-10-31
Total Disbursement in October of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
53,882.96
XDR
2021-11-15
Total Disbursement in November of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
4,403,497.56
XDR
2021-11-30
Total Disbursement in November of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,183,022
XDR
2021-12-31
Total Disbursement in December of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
157,363.82
XDR
2022-02-15
Total Disbursement in February of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
8,406,129
XDR
2022-02-28
Total Disbursement in February of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,556,662.06
XDR
2022-03-31
Total Disbursement in March of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,705,326.4
XDR
2022-04-30
Total Disbursement in April of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,351,478.21
XDR
2022-05-15
Total Disbursement in May of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
201,505.45
XDR
2022-05-31
Total Disbursement in May of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
3,135,024.89
XDR
2022-06-30
Total Disbursement in June of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
555,092.44
XDR
2022-07-31
Total Disbursement in July of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
380,712.81
XDR
2022-08-31
Total Disbursement in August of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
390,093.06
XDR
2022-11-15
Total Disbursement in November of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
311,693.34
XDR
2022-12-31
Total Disbursement in December of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,376,965.68
XDR
2023-02-15
Total Disbursement in February of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
2,067,266.38
XDR
2023-03-15
Total Disbursement in March of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
52,319.21
XDR
2023-04-15
Total Disbursement in April of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
50,418.86
XDR
2023-05-31
Total Disbursement in May of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
83,375.91
XDR
2023-06-15
Total Disbursement in June of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
504,219.08
XDR
2023-08-15
Total Disbursement in August of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
105,602.51
XDR
2023-09-15
Total Disbursement in September of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
145,159.15
XDR
2023-11-15
Total Disbursement in November of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
600,597.54
XDR
2023-11-30
Total Disbursement in November of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
442,151.69
XDR
2023-12-31
Total Disbursement in December of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
187,425.49
XDR
2024-04-15
Total Disbursement in April of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
422,786.76
XDR
2024-04-30
Total Disbursement in April of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
180,500.13
XDR
2024-09-30
Total Disbursement in September of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
44,235,717.39
XDR
Disbursement
Interest Payment ( 22 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2018-11-30
Total Interest Repayment in November of 2018
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
8,653.12
XDR
2019-05-31
Total Interest Repayment in May of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
14,185.38
XDR
2019-06-30
Total Interest Repayment in June of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
163.17
XDR
2019-12-31
Total Interest Repayment in December of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
16,646.86
XDR
2020-05-31
Total Interest Repayment in May of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
14,253.53
XDR
2020-06-30
Total Interest Repayment in June of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
14,016.68
XDR
2020-07-15
Total Interest Repayment in July of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
1,055.37
XDR
2020-11-30
Total Interest Repayment in November of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
42,126.45
XDR
2021-05-31
Total Interest Repayment in May of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
47,866.22
XDR
2021-11-30
Total Interest Repayment in November of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
44,232.62
XDR
2022-05-31
Total Interest Repayment in May of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
44,342.63
XDR
2022-11-30
Total Interest Repayment in November of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
133,588.53
XDR
2023-05-31
Total Interest Repayment in May of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
570,418.27
XDR
2023-11-30
Total Interest Repayment in November of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,166,353.78
XDR
2024-06-15
Total Interest Repayment in June of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,340,066.83
XDR
2024-09-30
Total Interest Repayment in September of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
413,717.08
XDR
2024-11-30
Total Interest Repayment in November of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,261,303.21
XDR
2024-12-15
Total Interest Repayment in December of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
56,139.3
XDR
2025-05-31
Total Interest Repayment in May of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,063,921.36
XDR
2025-05-31
Total Interest Repayment in May of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
52,860.55
XDR
2025-11-30
Total Interest Repayment in November of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
839,606.9
XDR
2026-03-31
Total Interest Repayment in March of 2026
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
53,148.73
XDR
Interest Payment
Loan Repayment ( 21 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2018-11-30
Total Loan Repayment in November of 2018
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
523,857.98
XDR
2019-05-31
Total Loan Repayment in May of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
506,422.88
XDR
2019-12-31
Total Loan Repayment in December of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
670,911.36
XDR
2020-02-29
Total Loan Repayment in February of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
629.26
XDR
2020-05-31
Total Loan Repayment in May of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
790,219.34
XDR
2020-06-30
Total Loan Repayment in June of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
790,507.3
XDR
2020-11-30
Total Loan Repayment in November of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
1,458,563.58
XDR
2021-05-31
Total Loan Repayment in May of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
1,762,281.82
XDR
2021-11-30
Total Loan Repayment in November of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
2,898,919.98
XDR
2022-05-31
Total Loan Repayment in May of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
3,586,057.89
XDR
2022-11-30
Total Loan Repayment in November of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
3,864,996.81
XDR
2023-05-31
Total Loan Repayment in May of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
4,291,078.15
XDR
2023-11-30
Total Loan Repayment in November of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
4,281,316.22
XDR
2024-06-15
Total Loan Repayment in June of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
4,394,836.97
XDR
2024-09-30
Total Loan Repayment in September of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
1,327,071.51
XDR
2024-11-30
Total Loan Repayment in November of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
4,452,071.14
XDR
2024-12-15
Total Loan Repayment in December of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
457,665.9
XDR
2025-05-31
Total Loan Repayment in May of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
4,432,808.6
XDR
2025-05-31
Total Loan Repayment in May of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
442,246.32
XDR
2025-11-30
Total Loan Repayment in November of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Bank
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
4,664,878.32
XDR
2026-03-31
Total Loan Repayment in March of 2026
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Clean Technology Fund
OFFICE NATIONAL DE L'ELECTRICITE
REF MA-COA-27
442,350.65
XDR
Loan Repayment
result( 5 )
output( 5 )
GLOSSARY
OutputResults of the activity that came about as a direct effect of your work and specific, what is done, and what communities are reached. For example, X number of individuals.
Output
indicator( 1 )
Electrical energy from wind and solar generation is valorised via optimal placement through energy storage
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
1.0 1.0
100%
2012-01-01 : 2023-12-31
Output
indicator( 1 )
Greenhouse gas emissions are avoided thanks to the electricity production of the Abdelmoumen STEP (350 MW)
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
1.0 1.0
100%
2012-01-01 : 2023-12-31
Output
indicator( 1 )
New 225 kV power lines to connect the Abdelmoumen STEP built
INDICATOR
Km
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
15.0 15.0
100%
2012-01-01 : 2023-12-31
Output
indicator( 1 )
The Abdelmoumen Pumped Storage Power Plant (STEP) with a total installed capacity of 350 MW (2x175 MW) built and operational
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
1.0 1.0
100%
2012-01-01 : 2023-12-31
Output
indicator( 1 )
The impact of intermittency of wind and solar generation is mitigated and the stability of the power transmission network in southern Morocco is improved
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
1.0 1.0
100%
2012-01-01 : 2023-12-31
African Development Bank
COMA
Moussa KONE
Power Engineer, PESD2
African Development Bank Group Headquarters Avenue Joseph Anoma 01 BP 1387 Abidjan 01, Côte d'Ivoire
other identifier( 1 )
REFERENCE IDENTIFIER OWNER ORG IDENTIFIER TYPE DESCRIPTION
46002 XM-DAC-46002
African Development Bank
Previous Reporting Organisation Identifier
CODE B1
No description provided
conditions( 2 )
NARRATIVE TYPE DESCRIPTION
Please see section 5 or 7 : Legal Documentation or Authority or Legal instruments and Authority
Policy The condition attached requires a particular policy to be implemented by the recipient
Please see section 5 or 7 : Legal Documentation or Authority or Legal instruments and Authority
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient