ACTIVITY TITLE
Zambia - Victoria Falls-Katima Mulilo 132 KV Interconnection Project
Zambie - Projet d’interconnexion électrique de 132 KV entre Victoria Falls et Katima Mulilo
Reported by
African Development Bank XM-DAC-46002 Multilateral
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Sub-national: Multi-first-level administrative areas 5 Multilateral (inflows) 2 Standard loan 421 ODA 10 Untied 1
Planned start date 1999-12-01
Planned end date 2006-12-31
Actual start date 2000-02-17
Actual end date 2006-12-31
activity status: Finalisation
Physical activity is complete or the final disbursement has been made, but the activity remains open pending financial sign off or M&E
WHO'S INVOLVED ( 5 )
PARTICIPATING ORG REFERENCE ROLE TYPE
African Development Fund
Funding Multilateral
Development Bank of Southern Africa (DBSA)
Funding Multilateral
Namibia Power Corporation (NamPower)
Funding Multilateral
ZESCO (Z) LTD
Implementing Government
Zambia Electricity Supply Corporation (ZESCO)
Funding Multilateral
Target Groups
Le projet devrait bénéficier à environ 74 000 personnes dans l'ouest de la Zambie. Dans la région de Caprivi en Namibie, le projet devrait profiter à une population rurale d’environ 25 000 personnes qui tirent leur subsistance de l’agriculture et du tourisme.
The project is expected to benefit about 74,000 people in Western Zambia. In Caprivi region in Namibia, the project is expected to benefit a rural population of about 25,000 who base their livelihood on agriculture and tourism.
General
Le projet proposé est un projet prioritaire de la politique du secteur de l’énergie des gouvernements de la Zambie et de la Namibie. Cela répondra essentiellement à la demande d'approvisionnement prévue dans l'ouest de la Zambie et à Katima Mulilo en Namibie. Le projet améliorera également les performances techniques du réseau en augmentant la fiabilité et la stabilité du réseau et en réduisant les pertes. Cela permettra : a) ZESCO à étendre l’approvisionnement en réseau national aux centres ruraux et périurbains de la Zambie occidentale; et (b) NamPower à mettre à la disposition des différents secteurs socio-économiques de la région de Caprivi une électricité relativement peu coûteuse et fiable. Le projet comprend la construction d'environ 190 km de réseau de transport à un seul circuit de 132 kV entre Victoria Falls (sud de la Zambie) et Katima Mulilo (ville frontalière du nord de la Namibie). La portion zambienne de la ligne fait environ 185 km, les 5 km restants étant situés en Namibie.
The proposed project is a priority project in the energy sector policy of the governments of Zambia and Namibia. It will essentially meet the forecast supply demand in Western Zambia and Katima Mulilo in Namibia. The project will also improve the technical network performance through increase in network reliability and stability and reduction of losses. It will enable (a) ZESCO to extend the national grid supply to the rural and peri-urban centres in Western Zambia; and (b) NamPower to make available relatively cheap and reliable electricity to the various socio-economic sectors at Caprivi region. The project involves the construction of approximately 190 km of single circuit 132 kV transmission network from Victoria Falls (southern Zambia) to Katima Mulilo (northern border town in Namibia). The Zambian portion of the line is approximately 185 km whilst the balance of 5 km is located in Namibia.
Objectives
Les objectifs du projet sont de fournir une électricité adéquate et fiable à une ville frontalière en Namibie et dans la région occidentale de la Zambie. Le projet vise principalement à renforcer l’approvisionnement actuel de Caprivi en Namibie, en prolongeant la ligne de transmission 132 kV reliant Victoria Falls (Zambie) à Katima-Mulilo (Namibie). Le projet renforcera également le réseau d'approvisionnement dans la région occidentale de la Zambie et contribuera ainsi à l'extension du réseau national d'approvisionnement aux centres ruraux de la région.
The objectives of the project are to provide adequate and reliable electricity to a boarder town in Namibia and the Western Region of Zambia. The project, primarily, aims at strengthening the existing supply to Caprivi in Namibia, by extending 132 kV transmission line from Victoria Falls (Zambia) to Katima-Mulilo (Namibia). The project will also strengthen the supply network in Western Region of Zambia and thus will advance the extension of the national grid supply to rural centres in the region.
recipient country ( 1 )
ZambiaZM
100
LOCATION ( 2 )
NAME DESCRIPTION POSITION CLASS REACH EXACTNESS
Caprivi Zipfel
ID 877332 (Global Admininistrative Unit Layers)
TYPE region RGN
-18 23 Other Topographical Feature Exact
Western Province
ID 896140 (Geonames)
TYPE first-order administrative division ADM1
-15 24 Administrative Region Approximate
country budget items ( 1 )
IATI Withdrawn ( 1 )
The budget identifier reported uses IATI budget identifier categories
3.6.1
100
sector ( 1 )
OECD DAC CRS 5 digit1( 1 )
The sector reported corresponds to an OECD DAC CRS 5-digit purpose code http://reference.iatistandard.org/codelists/Sector/
Energy sector policy, planning and administration23111
100
GLOSSARY
Energy sector policy, planning and administrationNo description provided
Financial Overview
Outgoing Commitment ( 1 )
Disbursement ( 2 )
Interest Payment ( 36 )
Loan Repayment ( 34 )
Budget ( 27 )
Outgoing Commitment
Disbursement
Interest Payment
Loan Repayment
Budget
Budget ( 27 )
START END TYPE STATUS VALUE
2000-02-17 2000-05-17 Original 440,101.204815
XDR
2000-05-17 2000-08-17 Original 440,101.204815
XDR
2000-08-17 2000-11-17 Original 440,101.204815
XDR
2000-11-17 2001-02-17 Original 440,101.204815
XDR
2001-02-17 2001-05-17 Original 440,101.204815
XDR
2001-05-17 2001-08-17 Original 440,101.204815
XDR
2001-08-17 2001-11-17 Original 440,101.204815
XDR
2001-11-17 2002-02-17 Original 440,101.204815
XDR
2002-02-17 2002-05-17 Original 440,101.204815
XDR
2002-05-17 2002-08-17 Original 440,101.204815
XDR
2002-08-17 2002-11-17 Original 440,101.204815
XDR
2002-11-17 2003-02-17 Original 440,101.204815
XDR
2003-02-17 2003-05-17 Original 440,101.204815
XDR
2003-05-17 2003-08-17 Original 440,101.204815
XDR
2003-08-17 2003-11-17 Original 440,101.204815
XDR
2003-11-17 2004-02-17 Original 440,101.204815
XDR
2004-02-17 2004-05-17 Original 440,101.204815
XDR
2004-05-17 2004-08-17 Original 440,101.204815
XDR
2004-08-17 2004-11-17 Original 440,101.204815
XDR
2004-11-17 2005-02-17 Original 440,101.204815
XDR
2005-02-17 2005-05-17 Original 440,101.204815
XDR
2005-05-17 2005-08-17 Original 440,101.204815
XDR
2005-08-17 2005-11-17 Original 440,101.204815
XDR
2005-11-17 2006-02-17 Original 440,101.204815
XDR
2006-02-17 2006-05-17 Original 440,101.204815
XDR
2006-05-17 2006-08-17 Original 440,101.204815
XDR
2006-08-17 2006-12-31 Original 440,101.204815
XDR
Budget
Transactions ( 73 )
Outgoing Commitment ( 1 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2000-02-17
REF 2100150001100
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
4,752,732.53
XDR
Outgoing Commitment
Disbursement ( 2 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2009-12-31
Total Disbursement till end of 2009
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
ZESCO (Z) LTD
4,516,317.49
XDR
2012-12-31
Total Disbursement in Fourth Quarter of 2012
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
ZESCO (Z) LTD
485,699.28
XDR
Disbursement
Interest Payment ( 36 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2009-12-31
Total Interest Repayment till end of 2009
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
230,790.32
XDR
2010-06-30
Total Interest Repayment in Second Quarter of 2010
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
14,415.66
XDR
2010-12-31
Total Interest Repayment in Fourth Quarter of 2010
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
14,139.88
XDR
2011-06-30
Total Interest Repayment in Second Quarter of 2011
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
14,303.23
XDR
2011-12-31
Total Interest Repayment in Fourth Quarter of 2011
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
13,998.01
XDR
2012-06-30
Total Interest Repayment in Second Quarter of 2012
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
14,155.94
XDR
2012-12-31
Total Interest Repayment in Fourth Quarter of 2012
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
13,932.26
XDR
2013-06-30
Total Interest Repayment in Second Quarter of 2013
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
14,266.83
XDR
2013-12-31
Total Interest Repayment in Fourth Quarter of 2013
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
14,242.41
XDR
2014-06-30
Total Interest Repayment in Second Quarter of 2014
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
14,311.95
XDR
2014-12-31
Total Interest Repayment in Fourth Quarter of 2014
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
13,850.5
XDR
2015-06-30
Total Interest Repayment in Second Quarter of 2015
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
13,309.68
XDR
2015-12-31
Total Interest Repayment in Fourth Quarter of 2015
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,887.24
XDR
2016-06-30
Total Interest Repayment in Second Quarter of 2016
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
13,079.88
XDR
2016-12-31
Total Interest Repayment in Fourth Quarter of 2016
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,924.34
XDR
2017-06-30
Total Interest Repayment in Second Quarter of 2017
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,941.93
XDR
2017-10-31
Total Interest Repayment in October of 2017
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
13,118
XDR
2018-04-30
Total Interest Repayment in April of 2018
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
13,297.85
XDR
2018-10-31
Total Interest Repayment in October of 2018
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,944.89
XDR
2019-04-30
Total Interest Repayment in April of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
3,064.23
XDR
2019-05-31
Total Interest Repayment in May of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
9,862.22
XDR
2019-10-31
Total Interest Repayment in October of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,669.86
XDR
2020-04-15
Total Interest Repayment in April of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,643.58
XDR
2020-10-31
Total Interest Repayment in October of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,684.97
XDR
2021-04-30
Total Interest Repayment in April of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,578.67
XDR
2021-10-31
Total Interest Repayment in October of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
12,070.42
XDR
2022-04-30
Total Interest Repayment in April of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Government Of Zambia
11,860.59
XDR
2022-11-15
Total Interest Repayment in November of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
11,275.92
XDR
2023-04-15
Total Interest Repayment in April of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
908.29
XDR
2023-04-30
Total Interest Repayment in April of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
10,583.7
XDR
2023-10-15
Total Interest Repayment in October of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
11,298.62
XDR
2024-04-15
Total Interest Repayment in April of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
11,205.91
XDR
2024-10-15
Total Interest Repayment in October of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
10,900.66
XDR
2025-04-15
Total Interest Repayment in April of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
10,623.32
XDR
2025-10-15
Total Interest Repayment in October of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
10,682.78
XDR
2026-04-15
Total Interest Repayment in April of 2026
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
10,714.09
XDR
Interest Payment
Loan Repayment ( 34 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2009-03-31
Total Loan Repayment till end of 2009
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
1,091,059.27
XDR
2010-06-30
Total Loan Repayment in Second Quarter of 2010
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
19,064.19
XDR
2010-12-31
Total Loan Repayment in Fourth Quarter of 2010
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
19,064.19
XDR
2011-06-30
Total Loan Repayment in Second Quarter of 2011
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
19,064.19
XDR
2011-12-31
Total Loan Repayment in Fourth Quarter of 2011
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
19,064.19
XDR
2012-06-30
Total Loan Repayment in Second Quarter of 2012
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
19,064.19
XDR
2012-12-31
Total Loan Repayment in Fourth Quarter of 2012
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
19,064.19
XDR
2013-06-30
Total Loan Repayment in Second Quarter of 2013
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
21,163.68
XDR
2013-12-31
Total Loan Repayment in Fourth Quarter of 2013
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
21,398.95
XDR
2014-06-30
Total Loan Repayment in Second Quarter of 2014
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
21,276.01
XDR
2014-12-31
Total Loan Repayment in Fourth Quarter of 2014
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
21,079.48
XDR
2015-06-30
Total Loan Repayment in Second Quarter of 2015
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,259.65
XDR
2015-12-31
Total Loan Repayment in Fourth Quarter of 2015
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,102.08
XDR
2016-06-30
Total Loan Repayment in Second Quarter of 2016
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,207.11
XDR
2016-12-31
Total Loan Repayment in Fourth Quarter of 2016
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,276.92
XDR
2017-06-30
Total Loan Repayment in Second Quarter of 2017
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,279.3
XDR
2017-10-31
Total Loan Repayment in October of 2017
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,843.62
XDR
2018-04-30
Total Loan Repayment in April of 2018
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,891.27
XDR
2018-10-31
Total Loan Repayment in October of 2018
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,814.67
XDR
2019-05-31
Total Loan Repayment in May of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,621.69
XDR
2019-10-31
Total Loan Repayment in October of 2019
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
20,673.84
XDR
2020-04-15
Total Loan Repayment in April of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
55,572.7
XDR
2020-10-31
Total Loan Repayment in October of 2020
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
57,102.47
XDR
2021-04-30
Total Loan Repayment in April of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
56,903.02
XDR
2021-10-31
Total Loan Repayment in October of 2021
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
56,505.08
XDR
2022-04-30
Total Loan Repayment in April of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
Government Of Zambia
55,619.16
XDR
2022-11-15
Total Loan Repayment in November of 2022
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
54,733.79
XDR
2023-04-30
Total Loan Repayment in April of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
55,832.79
XDR
2023-10-15
Total Loan Repayment in October of 2023
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
56,892.46
XDR
2024-04-15
Total Loan Repayment in April of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
56,654.3
XDR
2024-10-15
Total Loan Repayment in October of 2024
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
56,829.03
XDR
2025-04-15
Total Loan Repayment in April of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
55,855.9
XDR
2025-10-15
Total Loan Repayment in October of 2025
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
58,258.11
XDR
2026-04-15
Total Loan Repayment in April of 2026
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard loan 421
STATUS Untied 5
African Development Fund
Government Of Zambia
58,639.07
XDR
Loan Repayment
result( 9 )
output( 9 )
GLOSSARY
OutputResults of the activity that came about as a direct effect of your work and specific, what is done, and what communities are reached. For example, X number of individuals.
Output
indicator( 1 )
Distribution substations and transformers constructed or rehabilitated
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
1999
0.0
65.0 50.0
76%
1999-01-01 : 2006-12-31
Output
indicator( 1 )
Distribution substations and transformers constructed or rehabilitated
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
65.0 50.0
76%
1999-01-01 : 2006-12-31
Output
indicator( 1 )
Length of transmission and distribution lines rehabilitated or installed
INDICATOR
Km
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
190.0 231.0
100%
1999-01-01 : 2006-12-31
Output
indicator( 1 )
People benefiting from new electricity connections
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
99000.0 99000.0
100%
1999-01-01 : 2006-12-31
Output
indicator( 1 )
People benefiting from new electricity connections - of which women
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
Not provided
49500.0 49500.0
100%
1999-01-01 : 2006-12-31
Output
indicator( 1 )
Power capacity installed
INDICATOR
MW
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
1999
0.0
200.0 200.0
100%
1999-01-01 : 2006-12-31
Output
indicator( 1 )
Power capacity installed
INDICATOR
MW
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
200.0 200.0
100%
1999-01-01 : 2006-12-31
Output
indicator( 1 )
Power transmission lines
INDICATOR
Km
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
1999
0.0
190.0 231.0
100%
1999-01-01 : 2006-12-31
Output
indicator( 1 )
Transfer capacity of transmission lines
INDICATOR
MW
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
1999
0.0
20.0 190.0
100%
1999-01-01 : 2006-12-31
African Development Bank
RAM Babu
African Development Bank Group Headquarters Avenue Joseph Anoma 01 BP 1387 Abidjan 01, Côte d'Ivoire
other identifier( 1 )
REFERENCE IDENTIFIER OWNER ORG IDENTIFIER TYPE DESCRIPTION
46002 XM-DAC-46002
African Development Bank
Previous Reporting Organisation Identifier
CODE B1
No description provided
conditions( 2 )
NARRATIVE TYPE DESCRIPTION
Please see section 5 or 7 : Legal Documentation or Authority or Legal instruments and Authority
Policy The condition attached requires a particular policy to be implemented by the recipient
Please see section 5 or 7 : Legal Documentation or Authority or Legal instruments and Authority
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient