ACTIVITY TITLE
Somalia - Road Infrastructure Programme (RIP)
Somalie - Programme d'infrastructure routière (RIP)
Reported by
African Development Bank XM-DAC-46002 Multilateral
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Sub-national: Multi-first-level administrative areas 5 Multilateral (inflows) 2 Standard grant 110 ODA 10 Untied 1
DOCUMENTS ( 25 )
Appraisal Report APPLICATION/PDF EN Pre- and post-project impact appraisal Objectives / Purpose of activity Objectives / Purpose of activity Intended ultimate beneficiaries Conditions Budget Results, outcomes and outputs Appraisal Report APPLICATION/PDF FR Pre- and post-project impact appraisal Objectives / Purpose of activity Objectives / Purpose of activity Intended ultimate beneficiaries Conditions Budget Results, outcomes and outputs Environmental Study APPLICATION/PDF EN Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Environmental Study APPLICATION/PDF EN Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Environmental Study APPLICATION/PDF EN Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Environmental Study APPLICATION/PDF EN Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Environmental Study APPLICATION/PDF FR Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Evaluation Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Evaluation Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Evaluation Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Evaluation Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Evaluation Report APPLICATION/PDF EN Intended ultimate beneficiaries Review of project performance and evaluation Results, outcomes and outputs Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL EN Summary information about contract Contract Contract APPLICATION/VND.MS-EXCEL FR Summary information about contract Contract Expression of Interest APPLICATION/PDF EN Tender Expression of Interest APPLICATION/PDF EN Tender Expression of Interest APPLICATION/PDF EN Tender Expression of Interest APPLICATION/PDF EN Tender Expression of Interest APPLICATION/PDF EN Tender Expression of Interest APPLICATION/PDF EN Tender General Procurement Notice APPLICATION/PDF EN Tender Activity TEXT/HTML FR Activity web page Activity TEXT/HTML FR Activity web page
Planned start date 2019-07-19
Planned end date 2028-06-30
Actual start date 2019-08-27
activity status: Implementation
The activity is currently being implemented
WHO'S INVOLVED ( 4 )
PARTICIPATING ORG REFERENCE ROLE TYPE
African Development Fund
Funding Multilateral
European Union's Africa Investment Platform
Funding Multilateral
Ministry of Finance
Implementing Government
Transition Support Facility
Funding Multilateral
Target Groups
Direct beneficiaries of the project include communities, road users, businesses, exporter, importers, traders, farmers, transporters and regional governments in the target areas . The communities and the country as a whole will benefit from connectivity, reduced travel time and ransport costs and better quality of life. The project will provide employment opportunities for women and youth and the project communities will benefit indirectly from improved environment and economic activities. Capacity building and strengthening of the FGS MPWR&H and the infrastructure Ministries in the five FMSs (Galmudug, Hirshabelle, Jubaland, Puntland and South West) will lead to skills acquisition and enhanced performance. Finally, the technical assistance for Somaliland through preparation of Environmental and Social Impact Assessment (ESIA), Resettlement Action Plan (RAP), and feasibility study, preliminary and detailed engineering designs for the Lowyaddo –Farddaha-Borama road will contribute to readiness and easy implementation of the project when funds become available.
Les bénéficiaires directs du projet sont les communautés, les usagers de la route, les entreprises, les exportateurs, les importateurs, les commerçants, les agriculteurs, les transporteurs et les gouvernements régionaux des zones cibles. Les communautés et le pays dans l’ensemble bénéficieront de la connectivité, de la réduction du temps de déplacement et des coûts de transport,et d’une meilleure qualité de vie. Ce Projet offrira les opportunités d’emplois aux femmes et jeunes; les communautés du projet tireront parti aussi indirectement de l’amélioration de l’environnement et des activités économiques. Le renforcement des capacités et le renforcement duMPWR & H du FGS et des ministères de l’Infrastructure dans les cinq FMS (Galmudug, Hirshabelle, Jubaland, Puntland et Sud-Ouest) permettront d’acquérir des compétences et d’améliorer les performances. Enfin, l’assistance technique fournie au Somaliland par la préparation d’une étude d’impact environnemental et social (EIES), d’un plan d’action pour la réinstallation (PAR), d’une étude de faisabilité et d’études techniques préliminaires et détaillés pour la route Lowyaddo-Farddaha-Borama contribuera à la préparation et à la mise en œuvre aisée du projet lorsque les fonds seront disponibles.
General
Le programme d’infrastructure routière vise à améliorer la gestion du secteur routier au plan national et à améliorer la connectivité des usagers de la route dans les corridors routiers ciblés à des fins de réhabilitation, tout en renforçant les capacités des institutions fédérales et régionales chargées de la gestion des infrastructures routières. Ce programme comprend: i) la réhabilitation et l’aménagement par la pose d’une couche de bitume supplémentaire sur un tronçon de 82km (BeledWeyne-Kalabeyr, 22km et Dhusamareb-Qaradhi, 60km) d’une route bitumée existante Beled Weyne-Galkayo, longue de 327km, et de 7,3m de large; ii) la réhabilitation et l’aménagement par la pose d’une couche de bitume sur un tronçon de 85 km (Galkayo-Faratoyo) de la route bitumée existante Galkayo-Garowe,longue de 240km, et de 7,3m de large; iii) la réhabilitation et l’aménagement d’une piste existante Luuq, Ganane-Dolowlongue de 80km, et de 7,3m de large, reliant Luuq, Ganane-Dolow en une route en gravier, et iv) l’aménagement de la route Galkayo-Elgula,longue de 100km, et de 7,3m de large (tronçon de la route de desserte Galkayo-Hobyo, longue de 241km) en une route en gravier compacté, et la réalisation d’une étude de faisabilité, d’une étude d’impact environnemental et social et de la conception technique détaillée de la route Lowyaddo-Farddaha-Borama, d’une longueur de 280km.
The Road Infrastructure Programme aims to improve management of the road sector at the national level and improve transport connectivity for road users in the targeted road corridors for rehabilitation while reinforcing the capacities of federal and regional institutions that manage road infrastructure. The programme entails: (i) rehabilitation and surface dressing of 82km (BeledWeyne-Kalabeyr 22km; and Dhusamareb-Qaradhi 60km) of the existing 327km, 7.3m wide Beled Weyne-Galkayo paved road; (ii) rehabilitation and surface dressing of 85 km(Galkayo-Faratoyo) of the existing 240 km, 7.3 m wide Galkayo-Garowe paved road; (iii) rehabilitation and construction of the existing 80km, 7.3m wide Luuq, Ganane-Dolow earth road to gravel road standard; and (iv) new construction of 100 km, 7.3m wide Galkayo-Elgula (part of 241km Galkayo-Hobyo feeder road) to compacted gravel standard and Feasibility study, environmental and social impact assessment and detailed engineering design of 280 km Lowyaddo-Farddaha-Borama road.
Objectives
L’objectif général de développement du projet est d’appuyer et d’accélérer la croissance économique de la Somalie en fournissant des moyens de transport améliorés, fiables et d’un bon rapport coût-efficacité, dans l’optique d’améliorer l’accessibilité aux services et au transport des personnes et des biens, contribuant de ce fait au développement économique et social ainsi qu’au renforcement de la stabilité du pays. Les principaux résultats sont: une meilleure connectivité routière et un meilleur accès aux services de santé et d’éducation et aux marchés pour les communautés riveraines; réduction des temps et des coûts de déplacement; augmentation de la productivité économique, des possibilités d’emploi, intégration régionale et renforcement des capacités institutionnelles.
The project’s overall development objective is to support and improve Somalia’s economic growth by providing enhanced transport facilities that are reliable and cost effective, with a view to improving accessibility to services and transportation of persons and goods which will support economic and social development, as well as improving the stability of the country. The key outcomes include improved road connectivity and access to health and education services and markets for neighbouring communities; reduced travel times and costs; increased economic productivity, employment opportunities, regional integration and enhanced institutional capacity.
recipient country ( 1 )
SomaliaSO
100
LOCATION ( 3 )
NAME DESCRIPTION POSITION CLASS REACH EXACTNESS
Lower Juba
ID 56083 (Geonames)
TYPE first-order administrative division ADM1
0 42 Administrative Region Exact
Puntland
ID 8220543 (Geonames)
TYPE region RGN
9 49 Other Topographical Feature Exact
Galmudug
ID 8220544 (Geonames)
TYPE region RGN
6 48 Other Topographical Feature Exact
country budget items ( 1 )
IATI Withdrawn ( 1 )
The budget identifier reported uses IATI budget identifier categories
3.8.6
100
sector ( 1 )
OECD DAC CRS 5 digit1( 1 )
The sector reported corresponds to an OECD DAC CRS 5-digit purpose code http://reference.iatistandard.org/codelists/Sector/
National road construction21023
100
GLOSSARY
National road constructionConstruction or operation of national road transport systems and facilities.
Financial Overview
Outgoing Commitment ( 4 )
Disbursement ( 28 )
Budget ( 35 )
Outgoing Commitment
Disbursement
Budget
Budget ( 35 )
START END TYPE STATUS VALUE
2019-08-27 2019-11-27 Original 1,247,463.592286
XDR
2019-11-27 2020-02-27 Original 1,247,463.592286
XDR
2020-02-27 2020-05-27 Original 1,247,463.592286
XDR
2020-05-27 2020-08-27 Original 1,247,463.592286
XDR
2020-08-27 2020-11-27 Original 1,247,463.592286
XDR
2020-11-27 2021-02-27 Original 1,247,463.592286
XDR
2021-02-27 2021-05-27 Original 1,247,463.592286
XDR
2021-05-27 2021-08-27 Original 1,247,463.592286
XDR
2021-08-27 2021-11-27 Original 1,247,463.592286
XDR
2021-11-27 2022-02-27 Original 1,247,463.592286
XDR
2022-02-27 2022-05-27 Original 1,247,463.592286
XDR
2022-05-27 2022-08-27 Original 1,247,463.592286
XDR
2022-08-27 2022-11-27 Original 1,247,463.592286
XDR
2022-11-27 2023-02-27 Original 1,247,463.592286
XDR
2023-02-27 2023-05-27 Original 1,247,463.592286
XDR
2023-05-27 2023-08-27 Original 1,247,463.592286
XDR
2023-08-27 2023-11-27 Original 1,247,463.592286
XDR
2023-11-27 2024-02-27 Original 1,247,463.592286
XDR
2024-02-27 2024-05-27 Original 1,247,463.592286
XDR
2024-05-27 2024-08-27 Original 1,247,463.592286
XDR
2024-08-27 2024-11-27 Original 1,247,463.592286
XDR
2024-11-27 2025-02-27 Original 1,247,463.592286
XDR
2025-02-27 2025-05-27 Original 1,247,463.592286
XDR
2025-05-27 2025-08-27 Original 1,247,463.592286
XDR
2025-08-27 2025-11-27 Original 1,247,463.592286
XDR
2025-11-27 2026-02-27 Original 1,247,463.592286
XDR
2026-02-27 2026-05-27 Original 1,247,463.592286
XDR
2026-05-27 2026-08-27 Original 1,247,463.592286
XDR
2026-08-27 2026-11-27 Original 1,247,463.592286
XDR
2026-11-27 2027-02-27 Original 1,247,463.592286
XDR
2027-02-27 2027-05-27 Original 1,247,463.592286
XDR
2027-05-27 2027-08-27 Original 1,247,463.592286
XDR
2027-08-27 2027-11-27 Original 1,247,463.592286
XDR
2027-11-27 2028-02-27 Original 1,247,463.592286
XDR
2028-02-27 2028-06-30 Original 1,247,463.592286
XDR
Budget
Transactions ( 32 )
Outgoing Commitment ( 4 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2019-08-27
REF 2100155040169
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
GOVERNMENT OF SOMALIAMINISTRY OF FINANCE
7,500,000
XDR
2019-08-27
REF 5900155015755
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Government Of Somalia
2,000,000
XDR
2020-12-21
REF 5900155016410
FLOW ODA 10
AID Project-type interventions C01
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
GOVERNMENT OF SOMALIA MINISTRY OF FINANCE
2,630,000
XDR
2022-05-17
REF 5110155000760
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
European Union's Africa Investment Platform
Government Of Somalia
31,531,225.73
XDR
Outgoing Commitment
Disbursement ( 28 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2019-12-31
Total Disbursement in December of 2019
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
72,563.15
XDR
2019-12-31
Total Disbursement in December of 2019
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
50,878.01
XDR
2021-04-15
Total Disbursement in April of 2021
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
113,664.64
XDR
2021-11-15
Total Disbursement in November of 2021
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
52,905
XDR
2021-11-30
Total Disbursement in November of 2021
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
62,939.93
XDR
2021-12-31
Total Disbursement in December of 2021
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
157,371.35
XDR
2022-03-31
Total Disbursement in March of 2022
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
193,835.59
XDR
2022-04-30
Total Disbursement in April of 2022
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
89,712.7
XDR
2022-08-31
Total Disbursement in August of 2022
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
135,683.88
XDR
2022-11-15
Total Disbursement in November of 2022
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
140,176.06
XDR
2023-02-15
Total Disbursement in February of 2023
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
12,528.96
XDR
2023-04-15
Total Disbursement in April of 2023
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
464,260.02
XDR
2023-04-15
Total Disbursement in April of 2023
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
7,289.3
XDR
2023-04-30
Total Disbursement in April of 2023
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
132,774.48
XDR
2023-07-31
Total Disbursement in July of 2023
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
264,537.23
XDR
2023-09-30
Total Disbursement in September of 2023
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
19,902.19
XDR
2023-10-15
Total Disbursement in October of 2023
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
40,011.58
XDR
2023-11-30
Total Disbursement in November of 2023
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
295,204.94
XDR
2024-01-31
Total Disbursement in January of 2024
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
European Union's Africa Investment Platform
Ministry of Finance
367,633.07
XDR
2024-03-31
Total Disbursement in March of 2024
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
22,280.29
XDR
2024-04-15
Total Disbursement in April of 2024
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
21,904.38
XDR
2024-04-15
Total Disbursement in April of 2024
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
10,688.79
XDR
2024-05-15
Total Disbursement in May of 2024
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
32,939.83
XDR
2024-06-15
Total Disbursement in June of 2024
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
European Union's Africa Investment Platform
Ministry of Finance
140,095.71
XDR
2024-10-15
Total Disbursement in October of 2024
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
African Development Fund
Ministry of Finance
15,877.67
XDR
2024-10-31
Total Disbursement in October of 2024
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
European Union's Africa Investment Platform
Ministry of Finance
299,142.09
XDR
2025-03-15
Total Disbursement in March of 2025
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
Transition Support Facility
Ministry of Finance
13,663.9
XDR
2025-03-31
Total Disbursement in March of 2025
FLOW ODA 10
AID Other technical assistance D02
FINANCE Standard grant 110
STATUS Untied 5
European Union's Africa Investment Platform
Ministry of Finance
339,324.17
XDR
Disbursement
result( 20 )
output( 20 )
GLOSSARY
OutputResults of the activity that came about as a direct effect of your work and specific, what is done, and what communities are reached. For example, X number of individuals.
Output
indicator( 1 )
Audit Reports
INDICATOR
None
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
Not provided
Audit reports F/Y ENDED DEC 2023 SUBMITTED 27 JUNE 2024 AND UNDER REVIEW BY BANK
N/A
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Average speed on rehabilitated roads
INDICATOR
Km/h
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
60.0 30.0
50%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Average vehicle operating cost
INDICATOR
%
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
30.0 0.0
0%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Average Vehicle travel time
INDICATOR
Hour
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
1.4 3.2
100%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Communication and visibility
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
1.0 0.2
20%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Completed designs/reports
INDICATOR
None
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
Not provided
Complete designs/reports LOT 1 AND LOT 2 DESIGN SUBMITTED AND ACCEPTED
N/A
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Environmental and Social Management Plan (ESMP) implemented
INDICATOR
None
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
Not provided
EMSP implementation N/A NO WORKS ONGOING
N/A
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Increase in traffic - Average Annual Daily Traffic
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
327.0 274.0
83%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Length of roads rehabilitated to gravel standards
INDICATOR
Km
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
180.0 0.0
0%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Length of upgraded paved roads with surface dressing (TST)
INDICATOR
Km
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
175.0 0.0
0%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Local jobs opportunities created
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
300.0 0.0
0%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Local jobs opportunities created - of which are for women
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
Not provided
90.0 0.0
0%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Number of project-affected persons (PAPs) compensated and resettled
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
102.0 0.0
0%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Number of sensitization events and road safety campaigns
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
5.0 1.0
20%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Number of social amenities built
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
3.0 0.0
0%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Number of specialists procured
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
3.0 2.0
66%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Number of staff recruited
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
30.0 20.0
66%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Number of staff whose skills have been enhanced
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
200.0 25.0
12%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Number TAs recruited
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
6.0 2.0
33%
2019-01-01 : 2024-12-31
Output
indicator( 1 )
Plants introduced (seedlings, trees, etc.)
INDICATOR
Number
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
2500.0 0.0
0%
2019-01-01 : 2024-12-31
African Development Bank
RDGE
Wambui Winfred GICHURU
Transport Engineer, RDGE
+225 27 2026 8242
African Development Bank Group Headquarters Avenue Joseph Anoma 01 BP 1387 Abidjan 01, Côte d'Ivoire
other identifier( 1 )
REFERENCE IDENTIFIER OWNER ORG IDENTIFIER TYPE DESCRIPTION
46002 XM-DAC-46002
African Development Bank
Previous Reporting Organisation Identifier
CODE B1
No description provided
conditions( 2 )
NARRATIVE TYPE DESCRIPTION
Please see section 5 or 7 : Legal Documentation or Authority or Legal instruments and Authority
Policy The condition attached requires a particular policy to be implemented by the recipient
Please see section 5 or 7 : Legal Documentation or Authority or Legal instruments and Authority
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient