ACTIVITY TITLE
Trans-Hindukush Road Connectivity Project
Reported by
World Bank 44000 Multilateral
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Multilateral (inflows) 2
Project-type interventions C01
Untied 1
DOCUMENTS ( 26 )
Integrated Safeguards Data Sheet APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Integrated Safeguards Data Sheet APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Project Appraisal Document APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Project Information Document APPLICATION/PDF Objectives / Purpose of activity Intended ultimate beneficiaries Budget Project Information Document APPLICATION/PDF Objectives / Purpose of activity Intended ultimate beneficiaries Budget Agreement APPLICATION/PDF Objectives / Purpose of activity Conditions Budget Summary information about contract Memorandum of understanding (If agreed by all parties) Agreement APPLICATION/PDF Objectives / Purpose of activity Conditions Budget Summary information about contract Memorandum of understanding (If agreed by all parties) Financing Agreement APPLICATION/PDF Objectives / Purpose of activity Conditions Budget Summary information about contract Memorandum of understanding (If agreed by all parties) Implementation Completion and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Procurement Notices TEXT/HTML Tender Contract Awards TEXT/HTML Contract Project URL TEXT/HTML Activity web page
Planned start date 2014-10-28
Planned end date 2026-06-30
Actual start date 2015-10-20
Actual end date 2026-06-30
activity status: Implementation
The activity is currently being implemented
WHO'S INVOLVED ( 8 )
PARTICIPATING ORG REFERENCE ROLE TYPE
International Development Association
REF 44002
Funding Multilateral
International Development Association
REF 44002
Extending Multilateral
Islamic Republic of Afghanistan
Accountable
Islamic Republic of Afghanistan
Accountable
Ministry of Public Works
Implementing
Ministry of Public Works
Implementing
Ministry of Transport
Implementing
Ministry of Transport
Implementing
General
The objective of the Trans-Hindukush Road Connectivity Project for Afghanistan is to improve road transport connectivity across the Hindukush mountain range. There are two components to the project, the first component being Road construction and rehabilitation. This component will include: (i) civil works for the construction of the Baghlan to Bamiyan (B2B) road and the rehabilitation of the Salang road and tunnel, (ii) consulting services, including for the supervision of civil works and for regular technical audits by an independent international auditor to verify that road works have been executed in compliance with the technical specifications, and (iii) goods, which will include a small number of equipment items which MPW may need to keep the two roads open during the project period. The finalized technical design of the B2B road will include cable ducts and fiber optic cables. Technical specifications for the civil works will include labor intensive choices wherever feasible, such as masonry parapets instead of steel guardrails, and masonry retaining walls. It is estimated that within the total cost of Component, about US$ 170 million will be spent on the Baghlan to Bamiyan road, US$ 55 million will be spent on the Salang road and tunnel, while the remainder of US$ 15 million will be spent on goods and services benefitting both roads. The second component is the institutional support and project management. This component will be comprised of several subcomponents: definition and implementation of asset management arrangements for the trans-Hindukush roads, road safety, community engagement, training, capacity building and institutional development, and project management support.
Objectives
The project development objective is to improve road transport connectivity across the Hindukush mountain range.
recipient country ( 1 )
AfghanistanAF
100
LOCATION ( 20 )
NAME DESCRIPTION POSITION CLASS REACH EXACTNESS
Parwan
ID 0001131054 (Geonames)
35 68.916672 Administrative Region Activity Approximate
Wilāyat-e Bāmyān
ID 0001147239 (Geonames)
34.75 67.25 Administrative Region Activity Approximate
Wilāyat-e Baghlān
ID 0001147537 (Geonames)
35.75 69 Administrative Region Activity Approximate
Dōshī
ID 0007052902 (Geonames)
35.62088 68.665909 Administrative Region Activity Approximate
Talah wa Barfak
ID 0007052910 (Geonames)
35.275249 68.380676 Administrative Region Activity Approximate
Kahmard
ID 0007052911 (Geonames)
35.356949 67.775673 Administrative Region Activity Approximate
Sayghan
ID 0007052913 (Geonames)
35.118019 67.610458 Administrative Region Activity Approximate
Chārīkār
ID 0007054037 (Geonames)
34.98819 69.142036 Administrative Region Activity Approximate
Shibar
ID 0007732337 (Geonames)
34.865219 68.14492 Administrative Region Activity Approximate
Pul-e Khumri
ID 0001130490 (Geonames)
35.94458 68.715118 Populated Place Activity Approximate
Mazar-e Sharif
ID 0001133616 (Geonames)
36.709042 67.11087 Populated Place Activity Approximate
Kunduz
ID 0001135689 (Geonames)
36.728951 68.857002 Populated Place Activity Approximate
Kabul
ID 0001138958 (Geonames)
34.52813 69.172333 Populated Place Activity Approximate
Bamyan
ID 0001147242 (Geonames)
34.82156 67.827339 Populated Place Activity Approximate
Baghlan
ID 0001147540 (Geonames)
36.13068 68.70829 Populated Place Activity Approximate
Salangi
ID 0001409315 (Geonames)
36.230499 68.888397 Populated Place Activity Approximate
Maydanshakhr
ID 0001456960 (Geonames)
34.395611 68.86618 Populated Place Activity Approximate
Kōtal-e Tōnal-e Sālang
ID 0001127858 (Geonames)
35.318432 69.031822 Other Topographical Feature Activity Approximate
Kōtal-e Sālang
ID 0001127859 (Geonames)
35.31583 69.038887 Other Topographical Feature Activity Approximate
Hindū Kush
ID 0001139971 (Geonames)
35 71 Other Topographical Feature Activity Approximate
sector ( 7 )
OECD DAC CRS 5 digit1( 1 )
The sector reported corresponds to an OECD DAC CRS 5-digit purpose code http://reference.iatistandard.org/codelists/Sector/
National road construction21023
100
GLOSSARY
National road constructionConstruction or operation of national road transport systems and facilities.
Reporting Organisation99( 3 )
The sector reported corresponds to a sector vocabulary maintained by the reporting organisation for this activity
FY17 - Rural and Inter-Urban Roads TI
86
FY17 - ICT Infrastructure CI
10
FY17 - Public Administration - Transportation TF
4
Reporting Organisation 298( 3 )
The sector reported corresponds to a sector vocabulary maintained by the reporting organisation for this activity (if they are referencing more than one)
Rural Infrastructure and service delivery 000723
100
Public Private Partnerships 000023
10
Public Private Partnerships 000023
10
capital spend
The percentage of the total commitment that is for capital spending
100
Financial Overview
Outgoing Commitment ( 2 )
Disbursement ( 19 )
Budget ( 210 )
Outgoing Commitment
Disbursement
Budget
Budget ( 210 )
START END TYPE STATUS VALUE
2015-10-01 2015-10-31 Revised Indicative 0
USD
2015-10-01 2015-10-31 Original Indicative 789,382.49
USD
2015-11-01 2015-11-30 Revised Indicative 0
USD
2015-11-01 2015-11-30 Original Indicative 789,382.49
USD
2015-12-01 2015-12-31 Revised Indicative 0
USD
2015-12-01 2015-12-31 Original Indicative 789,382.49
USD
2016-01-01 2016-01-31 Revised Indicative 0
USD
2016-01-01 2016-01-31 Original Indicative 789,382.49
USD
2016-02-01 2016-02-29 Revised Indicative 0
USD
2016-02-01 2016-02-29 Original Indicative 789,382.49
USD
2016-03-01 2016-03-31 Revised Indicative 0
USD
2016-03-01 2016-03-31 Original Indicative 789,382.49
USD
2016-04-01 2016-04-30 Revised Indicative 0
USD
2016-04-01 2016-04-30 Original Indicative 789,382.49
USD
2016-05-01 2016-05-31 Revised Indicative 0
USD
2016-05-01 2016-05-31 Original Indicative 789,382.49
USD
2016-06-01 2016-06-30 Revised Indicative 0
USD
2016-06-01 2016-06-30 Original Indicative 789,382.49
USD
2016-07-01 2016-07-31 Revised Indicative 0
USD
2016-07-01 2016-07-31 Original Indicative 2,500,000
USD
2016-08-01 2016-08-31 Revised Indicative 0
USD
2016-08-01 2016-08-31 Original Indicative 2,500,000
USD
2016-09-01 2016-09-30 Revised Indicative 0
USD
2016-09-01 2016-09-30 Original Indicative 2,500,000
USD
2016-10-01 2016-10-31 Revised Indicative 0
USD
2016-10-01 2016-10-31 Original Indicative 2,500,000
USD
2016-11-01 2016-11-30 Revised Indicative 0
USD
2016-11-01 2016-11-30 Original Indicative 2,500,000
USD
2016-12-01 2016-12-31 Revised Indicative 0
USD
2016-12-01 2016-12-31 Original Indicative 2,500,000
USD
2017-01-01 2017-01-31 Revised Indicative 0
USD
2017-01-01 2017-01-31 Original Indicative 2,500,000
USD
2017-02-01 2017-02-28 Revised Indicative 0
USD
2017-02-01 2017-02-28 Original Indicative 2,500,000
USD
2017-03-01 2017-03-31 Revised Indicative 0
USD
2017-03-01 2017-03-31 Original Indicative 2,500,000
USD
2017-04-01 2017-04-30 Revised Indicative 0
USD
2017-04-01 2017-04-30 Original Indicative 2,500,000
USD
2017-05-01 2017-05-31 Revised Indicative 0
USD
2017-05-01 2017-05-31 Original Indicative 2,500,000
USD
2017-06-01 2017-06-30 Revised Indicative 0
USD
2017-06-01 2017-06-30 Original Indicative 2,500,000
USD
2017-07-01 2017-07-31 Revised Indicative 0
USD
2017-07-01 2017-07-31 Original Indicative 3,750,000
USD
2017-08-01 2017-08-31 Revised Indicative 0
USD
2017-08-01 2017-08-31 Original Indicative 3,750,000
USD
2017-09-01 2017-09-30 Revised Indicative 0
USD
2017-09-01 2017-09-30 Original Indicative 3,750,000
USD
2017-10-01 2017-10-31 Revised Indicative 0
USD
2017-10-01 2017-10-31 Original Indicative 3,750,000
USD
2017-11-01 2017-11-30 Revised Indicative 0
USD
2017-11-01 2017-11-30 Original Indicative 3,750,000
USD
2017-12-01 2017-12-31 Revised Indicative 0
USD
2017-12-01 2017-12-31 Original Indicative 3,750,000
USD
2018-01-01 2018-01-31 Revised Indicative 0
USD
2018-01-01 2018-01-31 Original Indicative 3,750,000
USD
2018-02-01 2018-02-28 Revised Indicative 0
USD
2018-02-01 2018-02-28 Original Indicative 3,750,000
USD
2018-03-01 2018-03-31 Revised Indicative 0
USD
2018-03-01 2018-03-31 Original Indicative 3,750,000
USD
2018-04-01 2018-04-30 Revised Indicative 0
USD
2018-04-01 2018-04-30 Original Indicative 3,750,000
USD
2018-05-01 2018-05-31 Revised Indicative 0
USD
2018-05-01 2018-05-31 Original Indicative 3,750,000
USD
2018-06-01 2018-06-30 Revised Indicative 0
USD
2018-06-01 2018-06-30 Original Indicative 3,750,000
USD
2018-07-01 2018-07-31 Revised Indicative 0
USD
2018-07-01 2018-07-31 Original Indicative 5,000,000
USD
2018-08-01 2018-08-31 Revised Indicative 0
USD
2018-08-01 2018-08-31 Original Indicative 5,000,000
USD
2018-09-01 2018-09-30 Revised Indicative 0
USD
2018-09-01 2018-09-30 Original Indicative 5,000,000
USD
2018-10-01 2018-10-31 Revised Indicative 0
USD
2018-10-01 2018-10-31 Original Indicative 5,000,000
USD
2018-11-01 2018-11-30 Revised Indicative 0
USD
2018-11-01 2018-11-30 Original Indicative 5,000,000
USD
2018-12-01 2018-12-31 Revised Indicative 0
USD
2018-12-01 2018-12-31 Original Indicative 5,000,000
USD
2019-01-01 2019-01-31 Revised Indicative 0
USD
2019-01-01 2019-01-31 Original Indicative 5,000,000
USD
2019-02-01 2019-02-28 Revised Indicative 0
USD
2019-02-01 2019-02-28 Original Indicative 5,000,000
USD
2019-03-01 2019-03-31 Revised Indicative 0
USD
2019-03-01 2019-03-31 Original Indicative 5,000,000
USD
2019-04-01 2019-04-30 Revised Indicative 0
USD
2019-04-01 2019-04-30 Original Indicative 5,000,000
USD
2019-05-01 2019-05-31 Revised Indicative 0
USD
2019-05-01 2019-05-31 Original Indicative 5,000,000
USD
2019-06-01 2019-06-30 Revised Indicative 0
USD
2019-06-01 2019-06-30 Original Indicative 5,000,000
USD
2019-07-01 2019-07-31 Revised Indicative 0
USD
2019-07-01 2019-07-31 Original Indicative 3,750,000
USD
2019-08-01 2019-08-31 Revised Indicative 0
USD
2019-08-01 2019-08-31 Original Indicative 3,750,000
USD
2019-09-01 2019-09-30 Revised Indicative 0
USD
2019-09-01 2019-09-30 Original Indicative 3,750,000
USD
2019-10-01 2019-10-31 Revised Indicative 0
USD
2019-10-01 2019-10-31 Original Indicative 3,750,000
USD
2019-11-01 2019-11-30 Revised Indicative 0
USD
2019-11-01 2019-11-30 Original Indicative 3,750,000
USD
2019-12-01 2019-12-31 Revised Indicative 0
USD
2019-12-01 2019-12-31 Original Indicative 3,750,000
USD
2020-01-01 2020-01-31 Revised Indicative 0
USD
2020-01-01 2020-01-31 Original Indicative 3,750,000
USD
2020-02-01 2020-02-29 Revised Indicative 0
USD
2020-02-01 2020-02-29 Original Indicative 3,750,000
USD
2020-03-01 2020-03-31 Revised Indicative 0
USD
2020-03-01 2020-03-31 Original Indicative 3,750,000
USD
2020-04-01 2020-04-30 Revised Indicative 0
USD
2020-04-01 2020-04-30 Original Indicative 3,750,000
USD
2020-05-01 2020-05-31 Revised Indicative 0
USD
2020-05-01 2020-05-31 Original Indicative 3,750,000
USD
2020-06-01 2020-06-30 Revised Indicative 0
USD
2020-06-01 2020-06-30 Original Indicative 3,750,000
USD
2020-07-01 2020-07-31 Revised Indicative 0
USD
2020-07-01 2020-07-31 Original Indicative 2,500,000
USD
2020-08-01 2020-08-31 Revised Indicative 0
USD
2020-08-01 2020-08-31 Original Indicative 2,500,000
USD
2020-09-01 2020-09-30 Revised Indicative 0
USD
2020-09-01 2020-09-30 Original Indicative 2,500,000
USD
2020-10-01 2020-10-31 Revised Indicative 0
USD
2020-10-01 2020-10-31 Original Indicative 2,500,000
USD
2020-11-01 2020-11-30 Revised Indicative 0
USD
2020-11-01 2020-11-30 Original Indicative 2,500,000
USD
2020-12-01 2020-12-31 Revised Indicative 0
USD
2020-12-01 2020-12-31 Original Indicative 2,500,000
USD
2021-01-01 2021-01-31 Revised Indicative 0
USD
2021-01-01 2021-01-31 Original Indicative 2,500,000
USD
2021-02-01 2021-02-28 Revised Indicative 0
USD
2021-02-01 2021-02-28 Original Indicative 2,500,000
USD
2021-03-01 2021-03-31 Revised Indicative 0
USD
2021-03-01 2021-03-31 Original Indicative 2,500,000
USD
2021-04-01 2021-04-30 Revised Indicative 0
USD
2021-04-01 2021-04-30 Original Indicative 2,500,000
USD
2021-05-01 2021-05-31 Revised Indicative 0
USD
2021-05-01 2021-05-31 Original Indicative 2,500,000
USD
2021-06-01 2021-06-30 Revised Indicative 0
USD
2021-06-01 2021-06-30 Original Indicative 2,500,000
USD
2021-07-01 2021-07-31 Revised Indicative 0
USD
2021-07-01 2021-07-31 Original Indicative 2,083,333.33
USD
2021-08-01 2021-08-31 Revised Indicative 0
USD
2021-08-01 2021-08-31 Original Indicative 2,083,333.33
USD
2021-09-01 2021-09-30 Revised Indicative 0
USD
2021-09-01 2021-09-30 Original Indicative 2,083,333.34
USD
2021-10-01 2021-10-31 Revised Indicative 0
USD
2021-10-01 2021-10-31 Original Indicative 2,083,333.33
USD
2021-11-01 2021-11-30 Revised Indicative 0
USD
2021-11-01 2021-11-30 Original Indicative 2,083,333.33
USD
2021-12-01 2021-12-31 Revised Indicative 0
USD
2021-12-01 2021-12-31 Original Indicative 2,083,333.34
USD
2022-01-01 2022-01-31 Revised Indicative 0
USD
2022-01-01 2022-01-31 Original Indicative 2,083,333.33
USD
2022-02-01 2022-02-28 Revised Indicative 0
USD
2022-02-01 2022-02-28 Original Indicative 2,083,333.33
USD
2022-03-01 2022-03-31 Revised Indicative 0
USD
2022-03-01 2022-03-31 Original Indicative 2,083,333.34
USD
2022-04-01 2022-04-30 Revised Indicative 0
USD
2022-04-01 2022-04-30 Original Indicative 2,083,333.33
USD
2022-05-01 2022-05-31 Revised Indicative 0
USD
2022-05-01 2022-05-31 Original Indicative 2,083,333.33
USD
2022-06-01 2022-06-30 Revised Indicative 0
USD
2022-06-01 2022-06-30 Original Indicative 2,083,333.34
USD
2022-07-01 2022-07-31 Revised Indicative 0
USD
2022-07-01 2022-07-31 Original Indicative 416,666.66
USD
2022-08-01 2022-08-31 Revised Indicative 0
USD
2022-08-01 2022-08-31 Original Indicative 416,666.67
USD
2022-09-01 2022-09-30 Revised Indicative 0
USD
2022-09-01 2022-09-30 Original Indicative 416,666.67
USD
2022-10-01 2022-10-31 Revised Indicative 0
USD
2022-10-01 2022-10-31 Original Indicative 416,666.66
USD
2022-11-01 2022-11-30 Revised Indicative 0
USD
2022-11-01 2022-11-30 Original Indicative 416,666.67
USD
2022-12-01 2022-12-31 Revised Indicative 0
USD
2022-12-01 2022-12-31 Original Indicative 416,666.67
USD
2023-01-01 2023-01-31 Revised Indicative 0
USD
2023-01-01 2023-01-31 Original Indicative 416,666.66
USD
2023-02-01 2023-02-28 Revised Indicative 0
USD
2023-02-01 2023-02-28 Original Indicative 416,666.67
USD
2023-03-01 2023-03-31 Revised Indicative 0
USD
2023-03-01 2023-03-31 Original Indicative 416,666.67
USD
2023-04-01 2023-04-30 Revised Indicative 0
USD
2023-04-01 2023-04-30 Original Indicative 416,666.66
USD
2023-05-01 2023-05-31 Revised Indicative 0
USD
2023-05-01 2023-05-31 Original Indicative 416,666.67
USD
2023-06-01 2023-06-30 Revised Indicative 0
USD
2023-06-01 2023-06-30 Original Indicative 416,666.67
USD
2023-07-01 2023-07-31 Original Indicative 0
USD
2023-07-01 2023-07-31 Revised Indicative 0
USD
2023-08-01 2023-08-31 Original Indicative 0
USD
2023-08-01 2023-08-31 Revised Indicative 0
USD
2023-09-01 2023-09-30 Original Indicative 0
USD
2023-09-01 2023-09-30 Revised Indicative 0
USD
2023-10-01 2023-10-31 Original Indicative 0
USD
2023-10-01 2023-10-31 Revised Indicative 0
USD
2023-11-01 2023-11-30 Original Indicative 0
USD
2023-11-01 2023-11-30 Revised Indicative 0
USD
2023-12-01 2023-12-31 Original Indicative 0
USD
2023-12-01 2023-12-31 Revised Indicative 0
USD
2024-01-01 2024-01-31 Original Indicative 0
USD
2024-01-01 2024-01-31 Revised Indicative 0
USD
2024-02-01 2024-02-29 Original Indicative 0
USD
2024-02-01 2024-02-29 Revised Indicative 0
USD
2024-03-01 2024-03-31 Original Indicative 0
USD
2024-03-01 2024-03-31 Revised Indicative 0
USD
2024-04-01 2024-04-30 Original Indicative 0
USD
2024-04-01 2024-04-30 Revised Indicative 0
USD
2024-05-01 2024-05-31 Original Indicative 0
USD
2024-05-01 2024-05-31 Revised Indicative 0
USD
2024-06-01 2024-06-30 Original Indicative 0
USD
2024-06-01 2024-06-30 Revised Indicative 0
USD
Budget
Transactions ( 21 )
Outgoing Commitment ( 2 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2015-10-31
Total Commitment in October Month of 2015
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
250,000,000
USD
2020-06-30
Total Commitment Cancellations in June Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-100,003,630
USD
Outgoing Commitment
Disbursement ( 19 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2016-06-30
Total Disbursement in June Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
5,000,000
USD
2016-07-31
Total Disbursement in July Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
8,500,000
USD
2017-03-31
Total Disbursement in March Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
740,306
USD
2017-04-30
Total Disbursement in April Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,078,297
USD
2017-09-30
Total Disbursement in September Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
146,023
USD
2018-03-31
Total Disbursement in March Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
5,482,247
USD
2018-06-30
Total Disbursement in June Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
6,431,278
USD
2019-06-30
Total Disbursement in June Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
12,201,585
USD
2019-09-30
Total Disbursement in September Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
900,000
USD
2019-12-31
Total Disbursement in December Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
7,448,128
USD
2020-05-31
Total Disbursement in May Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,400,000
USD
2020-06-30
Total Disbursement in June Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,445,272
USD
2020-09-30
Total Disbursement in September Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
675,078
USD
2020-10-31
Total Disbursement in October Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,290,830
USD
2021-02-28
Total Disbursement in February Month of 2021
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
3,001,662
USD
2021-05-31
Total Disbursement in May Month of 2021
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
4,883,455
USD
2025-02-28
Total Disbursement in February Month of 2025
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
113,456
USD
2025-05-31
Total Disbursement in May Month of 2025
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,193,153
USD
2025-10-31
Total Disbursement in October Month of 2025
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
110,446
USD
Disbursement
result( 27 )
output( 22 )
outcome( 5 )
GLOSSARY
No description provided
OutcomeResults of the activity that produce an effect on the overall communities or issues you serve. For example lower rate of infection after a vaccination programme.
indicator( 1 )
rmediate Results Indicator
INDICATOR
Pavement Completion Rate on B2B road
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
2015
0.00
100.00 2.00
2%
2015-05-18 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Pavement Completion Rate on B2B road
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
2015
0.00
100.00 2.00
2%
2015-05-18 : 2022-12-30
indicator( 1 )
rmediate Results Indicator
INDICATOR
Earthworks completion rate on B2B road
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
2015
0.00
100.00 40.00
40%
2015-05-18 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Earthworks completion rate on B2B road
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
2015
0.00
100.00 40.00
40%
2015-05-18 : 2022-07-29
indicator( 1 )
rmediate Results Indicator
INDICATOR
Outreach to adult female members of PAP households
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
2015
0.00
85.00 75.00
88%
2015-06-01 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Outreach to adult female members of PAP households
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
2015
0.00
85.00 75.00
88%
2015-06-01 : 2022-12-30
indicator( 1 )
rmediate Results Indicator
INDICATOR
Culturally appropriate rest facilities at appropriate locations
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2015
N
Y N
N/A
2015-06-01 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Culturally appropriate rest facilities at appropriate locations
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2015
No
Yes No
N/A
2015-06-01 : 2022-12-30
indicator( 1 )
rmediate Results Indicator
INDICATOR
Grievances Redress System operational with registry of complaints and recording of response times
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2015
N
Y Y
N/A
2015-06-15 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Road Safety Audit of Engineering Design done and recommendations implemented during civil works
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2015
N
Y Y
N/A
2015-06-15 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Grievances Redress System operational with registry of complaints and recording of response times
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2015
No
Yes Yes
N/A
2015-06-15 : 2016-03-15
indicator( 1 )
rmediate Results Indicator
INDICATOR
Road Safety Audit of Engineering Design done and recommendations implemented during civil works
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2015
No
Yes Yes
N/A
2015-06-15 : 2016-11-15
indicator( 1 )
rmediate Results Indicator
INDICATOR
Roads constructed, non-rural
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
152.00 0.00
0%
2015-06-25 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Roads constructed, non-rural
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
152.00 0.00
0%
2015-06-25 : 2022-12-30
indicator( 1 )
rmediate Results Indicator
INDICATOR
Mechanism for Management, Maintenance and Operation of both the B2B road and the Salang Pass established and functioning
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2015
N
Y N
N/A
2015-06-30 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Mechanism for Management, Maintenance and Operation of both the B2B road and the Salang Pass established and functioning
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2015
No
Yes No
N/A
2015-06-30 : 2021-11-15
indicator( 1 )
rmediate Results Indicator
INDICATOR
Capacity Building: Compliance with Performance indicators for MPW project implementation capacity
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
7.00 0.00
0%
2015-07-28 : 2020-08-10
indicator( 1 )
rmediate Results Indicator
INDICATOR
Fiber Optic Cable installed along B2B road
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
152.00 0.00
0%
2015-07-28 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Fiber Optic Cable installed along B2B road
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
152.00 0.00
0%
2015-07-28 : 2022-12-30
indicator( 1 )
rmediate Results Indicator
INDICATOR
Capacity Building: Compliance with Performance indicators for MPW project implementation capacity
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
7.00 0.00
0%
2015-07-28 : 2022-12-30
indicator( 1 )
rmediate Results Indicator
INDICATOR
Consultations with civil society and project-affected persons, with at least 30% of consultations focused on women
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
18.00 20.00
100%
2015-07-28 : 2020-08-17
indicator( 1 )
rmediate Results Indicator
INDICATOR
Consultations with civil society and project-affected persons, with at least 30% of consultations focused on women
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
18.00 20.00
100%
2015-07-28 : 2022-11-15
Outcome
indicator( 1 )
Indicator
INDICATOR
Direct project beneficiaries
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
0.00
1462000.00 0.00
0%
2015-05-18 : 2020-08-10
Outcome
indicator( 1 )
Indicator
INDICATOR
Average travel time for trucks on Baghlan to Bamiyan road (Dushi to Shibar)
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
24.00
5.00 24.00
0%
2015-05-18 : 2020-08-10
Outcome
indicator( 1 )
Indicator
INDICATOR
Average travel time for trucks on Baghlan to Bamiyan road (Dushi to Shibar)
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
24.00
5.00 24.00
0%
2015-05-18 : 2022-12-30
Outcome
indicator( 1 )
Indicator
INDICATOR
Average number of days per year when road crossing of Hindukush mountain range is not possible
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
20.00
7.00 14.00
46%
2015-06-30 : 2022-12-30
Outcome
indicator( 1 )
Indicator
INDICATOR
Average number of days per year when road crossing of Hindukush mountain range is not possible
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2015
20.00
14.00 20.00
0%
2015-06-30 : 2020-08-10
General Enquiries
The World Bank
Kulwinder Singh Rao
+1-202-473-1000
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
conditions( 3 )
NARRATIVE TYPE DESCRIPTION
Finance Agreement: Existing IP Consultant contract | Description: The Recipient, through MPW, shall maintain until August 31, 2016or such other date as may be agreed between the Recipient and the Association, the services of the Implementation Consultant underthe existing contract to assist MPW in the day-to-day implementation, coordination and monitoring of the Project. | Frequency:CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement: New IP Consultant contract | Description: By no later than August 31, 2016, the Recipient, through MPW, shallcontract for a period agreed between the Recipient and the Association the services of a duly qualified and experiencedImplementation Consultant team, with qualifications and under terms of reference satisfactory to the Association. | Due Date:31-Aug-2016
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement: Recurrent MPW PMT capacity assessment | Description: The recipient shall, every six months during the entireperiod of the Implementation Consultant's contract, carry out together with the Association, an in-depth review of theimplementation capacity of MPW and the PMT in order to determine their readiness to assume full implementation responsibilitywithout IC support and make decisions on the necessary follow-on implementation arrangements. | Frequency: Semi Annual
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient