ACTIVITY TITLE
DSIF - Bolivia - Three Wind Farms Project - Technical Assistance
Reported by
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Bilateral 1
Project-type interventions C01
Standard grant 110 ODA 10 2
Planned start date 2017-01-01
Planned end date 2025-12-31
Actual start date 2020-12-06
activity status: Implementation
The activity is currently being implemented
WHO'S INVOLVED ( 2 )
PARTICIPATING ORG REFERENCE ROLE TYPE
Investeringsfonden for Udviklingslande
CRS Public corporations
Accountable Government
Ministry of Foreign Affairs, Denmark
Funding Government
Objectives
Bolivia - Three Wind Farms Project
tag( 2 )
DESCRIPTION CODE VOCABULARY
By 2030, increase substantially the share of renewable energy in the global energy mix 7.2 UN Sustainable Development Goals (SDG) Targets
By 2030, increase substantially the share of renewable energy in the global energy mix 7.2 UN Sustainable Development Goals (SDG) Targets
policy marker( 9 )
CODELIST SIGNIFICANCE VOCABULARY DESCRIPTION
Aid Targeting the Objectives of the Convention on Biological Diversity not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Aid Targeting the Objectives of the Convention to Combat Desertification not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Aid Targeting the Objectives of the Framework Convention on Climate Change - Adaptation not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Aid Targeting the Objectives of the Framework Convention on Climate Change - Mitigation principal objective OECD DAC CRS Principal (primary) policy objectives are those which can be identified as being fundamental in the design and impact of the activity and which are an explicit objective of the activity. They may be selected by answering the question "Would the activity have been undertaken without this objective?"
Aid to Environment principal objective OECD DAC CRS Principal (primary) policy objectives are those which can be identified as being fundamental in the design and impact of the activity and which are an explicit objective of the activity. They may be selected by answering the question "Would the activity have been undertaken without this objective?"
Gender Equality not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Participatory Development/Good Governance not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Reproductive, Maternal, Newborn and Child Health (RMNCH) not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Trade Development not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
recipient country ( 1 )
Bolivia (Plurinational State of)BO
100
country budget items ( 1 )
Reporting Organisation ( 1 )
The budget identifier reported corresponds to categories that are specific to the reporting organisation
707
100
sector ( 4 )
OECD DAC CRS 5 digit1( 1 )
The sector reported corresponds to an OECD DAC CRS 5-digit purpose code http://reference.iatistandard.org/codelists/Sector/
Wind energy23240
100
GLOSSARY
Wind energyWind energy for water lifting and electric power generation.
OECD DAC CRS 3 digit2( 1 )
The sector reported corresponds to an OECD DAC CRS 3-digit purpose code http://reference.iatistandard.org/codelists/SectorCategory/
Energy generation, renewable sources232
100
GLOSSARY
Energy generation, renewable sourcesNo description provided
SDG Target8( 2 )
A value from the second-level list of UN sustainable development goals (SDGs) (e.g. ‘1.1’) http://reference.iatistandard.org/codelists/unsdg-targets
7.2 7.2
100
7.2 7.2
100
Financial Overview
Disbursement ( 1 )
Budget ( 3 )
Disbursement
Budget
Budget ( 3 )
START END TYPE STATUS VALUE
2020-10-01 2020-12-31 Original 238,923,753
DKK
2021-07-01 2021-09-30 Original -800,000
DKK
2024-10-01 2024-12-31 Original -31,717,917
DKK
Budget
Transactions ( 1 )
Disbursement ( 1 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2024-12-13
FLOW ODA 10
FINANCE Standard grant 110
STATUS Untied 5
Ministry of Foreign Affairs, Denmark
-31,717,917.72
DKK
Disbursement
result( 1 )
output( 1 )
GLOSSARY
OutputResults of the activity that came about as a direct effect of your work and specific, what is done, and what communities are reached. For example, X number of individuals.
Output
indicator( 1 )
Process according to plan
REFERENCE
VOCAB 99
CODE 272854
INDICATOR
Proces indicators
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
Not provided
Tender complete, contract signed Tender complete, contract signed
N/A
2017-01-01 : 2017-12-31
No dimension has been provided
No location has been provided
Not provided
Progress of implementation according to contract of works Progress of implementation according to contract of works
N/A
2018-01-01 : 2018-12-31
No dimension has been provided
No location has been provided
Not provided
Progress of implementation according to contract of works Progress of implementation according to contract of works
N/A
2019-01-01 : 2019-12-31
No dimension has been provided
No location has been provided
Not provided
Progress of implementation according to contract of works Delayed due to, among other things, civil unrest and blockades during the Bolivian protests in October-November 2019 and the Covid-19 lockdown of the country in 2020.
N/A
2020-01-01 : 2020-12-31
No dimension has been provided
No location has been provided
Not provided
Commissioning Commissioning on November 30th 2021
N/A
2021-01-01 : 2021-12-31
No dimension has been provided
No location has been provided
Not provided
Progress of implementation according to contract of works Progress of implementation according to contract of works. 29 windmills have been taken over, Windturbine nr. 30 needs new blades before can be taken over in 2023.
N/A
2022-01-01 : 2022-12-31
No dimension has been provided
No location has been provided
Not provided
End of guarantee verification N/A
N/A
2023-01-01 : 2023-12-31
General Enquiries
MINISTRY OF FOREIGN AFFAIRS, DENMARK
Green Diplomacy and Climate
Asiatisk Plads 2, 1448 København K, Denmark
other identifier( 2 )
REFERENCE IDENTIFIER OWNER ORG IDENTIFIER TYPE DESCRIPTION
Ministry of Foreign Affairs, Denmark
2016-17613
Reporting Organisation's internal activity identifier
CODE A1
No description provided
Ministry of Foreign Affairs, Denmark
2016001201
CRS Activity identifier
CODE A2
No description provided