ACTIVITY TITLE
Partners for Resilience: Mali
Reported by
The Netherlands Red Cross NL-KVK-40409352 International NGO
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Bilateral 1
Project-type interventions C01
Standard grant 110 Private Development Finance 30 Untied 2
Planned end date 2021-01-30
Actual start date 2015-12-31
activity status: Implementation
The activity is currently being implemented
WHO'S INVOLVED ( 3 )
PARTICIPATING ORG REFERENCE ROLE TYPE
Mali Red Cross
Implementing National NGO
The Netherlands Red Cross
Funding International NGO
The Netherlands Red Cross
Accountable International NGO
Target Groups
Actions relate to different actors. Four groups are distinguished: Communities, Civil Society organisations (Red Cross, plus PfR partners, other CSOs, organised communities), Government (at various levels), and the private sector. Beneficiaries of the programme are vulnerable communities in disaster-prone conditions.
Objectives
Partners for Resilience strengthens community resilience by working with civil society organisations on reducing risks and strengthening livelihoods of vulnerable communities, with specific attention for marginalized groups and women. The Integrated Risk Management (IRM) approach bridges time- and spatial scales. It integrates the urgent attention needed for changing risks due to changes in hazards, exposure and vulnerability. IRM includes a specific focus on ecosystem degradation, locally and in the wider landscape, as well as changes in hazards due to climate change (in relation to current risks, nearterm changes and longer-term shifts in climate patterns). IRM thus integrates elements from disaster risk reduction (DRR), climate change adaptation (CCA) and ecosystem management and restoration (EMR).
General
People world-wide live in disaster-prone areas. Disasters damage the eco-systems they live in and upon which their livelihoods depend. Their vulnerability to disasters is aggravated by climate change, which increases the frequency, scale and unpredictability of disasters. Eco-systems, if protected and managed well, can play an important role in mitigating the impact of disasters (holding more excess water, sheltering form storms).
General
The Strategic Partnership of Partners for Resilience (PfR) is aimed at promoting and improving (attention for) Integrated Risk Management (IRM) in policies, investments and practices of key stakeholders (governments, private sector, institutions and others). The ultimate aim is to improve resilience of vulnerable communities who are confronted with disaster risks though better laws and regulations, IRM-proof investments, and enhanced practices that take better account of their potential to reduce risks. This project focuses on improving resilience in vulnerable communities in Mali. The project in Mali is under the lead of Wetlands International, in cooperation with the organisations Mali Red Cross, Netherlands Red Cross, Red Cross Climate Centre, and Care Mali.
General
This project focuses on vulnerable communities in Mali. General remarks PfR Mali partners work together on all trajectories in the Inner Niger Delta, the Sourou/ Volta River and at national level. In 2018 the partners are starting up trajectories/activities in the Senegal River Basin.
policy marker( 1 )
CODELIST SIGNIFICANCE VOCABULARY DESCRIPTION
Aid Targeting the Objectives of the Framework Convention on Climate Change - Adaptation significant objective OECD DAC CRS Significant (secondary) policy objectives are those which, although important, were not the prime motivation for undertaking the activity.
recipient country ( 1 )
MaliML
100
LOCATION ( 3 )
NAME DESCRIPTION POSITION CLASS REACH EXACTNESS
Mopti
ID node/1717464540 (OpenStreetMap)
14.4879631 -4.1905986
Bamako
ID node/27564954 (OpenStreetMap)
12.6493194 -8.0003371
Kayes
ID node/277932033 (OpenStreetMap)
14.443406 -11.437914
sector ( 4 )
OECD DAC CRS 5 digit1( 1 )
The sector reported corresponds to an OECD DAC CRS 5-digit purpose code http://reference.iatistandard.org/codelists/Sector/
Multi-hazard response preparedness74020
100
GLOSSARY
Multi-hazard response preparednessBuilding the responsiveness, capability and capacity of international, regional and national humanitarian actors to disasters. Support to the institutional capacities of national and local government, specialised humanitarian bodies, and civil society organisations to anticipate, respond and recover from the impact of potential, imminent and current hazardous events and emergency situations that pose humanitarian threats and could call for a humanitarian response. This includes risk analysis and assessment, mitigation, preparedness, such as stockpiling of emergency items and training and capacity building aimed to increase the speed and effectiveness of lifesaving assistance delivered in the occurrence of crisis.
Reporting Organisation99( 2 )
The sector reported corresponds to a sector vocabulary maintained by the reporting organisation for this activity
Drought DR
50
Flood FL
50
Reporting Organisation 298( 1 )
The sector reported corresponds to a sector vocabulary maintained by the reporting organisation for this activity (if they are referencing more than one)
Prevention / Mitigation 4
100
Financial Overview
Outgoing Commitment ( 6 )
Disbursement ( 18 )
Expenditure ( 61 )
Budget ( 1 )
Outgoing Commitment
Disbursement
Expenditure
Budget
Budget ( 1 )
START END TYPE STATUS VALUE
2015-12-31 2021-01-30 Original 1,272,719
EUR
Budget
Transactions ( 85 )
Outgoing Commitment ( 6 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2017-12-31
Commitment
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
761,678
EUR
2020-12-31
Commitment
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
-27,529
EUR
2020-12-31
Commitment
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
2,599
EUR
2021-12-31
Commitment
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
-2,599
EUR
2021-12-31
Commitment
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
12,254
EUR
2023-04-30
Commitment
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
5,233
EUR
Outgoing Commitment
Disbursement ( 18 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2016-07-12
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
50,000
EUR
2016-10-31
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
251
EUR
2016-12-31
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
-2,102
EUR
2016-12-31
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
5,000
EUR
2017-06-07
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
-44,690
EUR
2017-06-07
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
1,421
EUR
2017-06-07
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
44,690
EUR
2017-07-26
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
97,809
EUR
2018-05-01
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
136,123
EUR
2018-11-14
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
61
EUR
2018-12-03
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
51,205
EUR
2018-12-20
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
2,719
EUR
2019-02-19
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
134,296
EUR
2019-06-01
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
15,043
EUR
2019-08-08
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
71,676
EUR
2020-02-17
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
173,246
EUR
2021-01-19
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
14,901
EUR
2022-04-14
Disbursement
The Netherlands Red Cross
International NGO
Mali Red Cross
National NGO
-13
EUR
Disbursement
Expenditure ( 61 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2016-04-01
Expenditure
The Netherlands Red Cross
International NGO
46
EUR
2016-05-01
Expenditure
The Netherlands Red Cross
International NGO
184
EUR
2016-06-15
Expenditure
The Netherlands Red Cross
International NGO
300
EUR
2016-07-01
Expenditure
The Netherlands Red Cross
International NGO
38,437
EUR
2016-07-12
Expenditure
The Netherlands Red Cross
International NGO
8,000
EUR
2016-07-31
Expenditure
The Netherlands Red Cross
International NGO
4,032
EUR
2016-08-24
Expenditure
The Netherlands Red Cross
International NGO
181
EUR
2016-08-31
Expenditure
The Netherlands Red Cross
International NGO
1,423
EUR
2016-12-31
Expenditure
The Netherlands Red Cross
International NGO
70,674
EUR
2017-01-01
Expenditure
The Netherlands Red Cross
International NGO
5,096
EUR
2017-02-01
Expenditure
The Netherlands Red Cross
International NGO
6,716
EUR
2017-03-01
Expenditure
The Netherlands Red Cross
International NGO
11,752
EUR
2017-04-01
Expenditure
The Netherlands Red Cross
International NGO
5,107
EUR
2017-05-01
Expenditure
The Netherlands Red Cross
International NGO
5,070
EUR
2017-06-01
Expenditure
The Netherlands Red Cross
International NGO
13,971
EUR
2017-07-01
Expenditure
The Netherlands Red Cross
International NGO
4,049
EUR
2017-08-01
Expenditure
The Netherlands Red Cross
International NGO
397
EUR
2017-09-01
Expenditure
The Netherlands Red Cross
International NGO
18,725
EUR
2017-11-01
Expenditure
The Netherlands Red Cross
International NGO
29
EUR
2017-12-01
Expenditure
The Netherlands Red Cross
International NGO
39,778
EUR
2017-12-31
Expenditure
The Netherlands Red Cross
International NGO
-895
EUR
2018-01-01
Expenditure
The Netherlands Red Cross
International NGO
5,651
EUR
2018-02-01
Expenditure
The Netherlands Red Cross
International NGO
6,762
EUR
2018-03-01
Expenditure
The Netherlands Red Cross
International NGO
8,639
EUR
2018-03-23
Expenditure
The Netherlands Red Cross
International NGO
12,119
EUR
2018-04-01
Expenditure
The Netherlands Red Cross
International NGO
6,494
EUR
2018-05-01
Expenditure
The Netherlands Red Cross
International NGO
4,660
EUR
2018-06-01
Expenditure
The Netherlands Red Cross
International NGO
8,960
EUR
2018-07-01
Expenditure
The Netherlands Red Cross
International NGO
6,727
EUR
2018-07-31
Expenditure
The Netherlands Red Cross
International NGO
367
EUR
2018-08-01
Expenditure
The Netherlands Red Cross
International NGO
7,295
EUR
2018-09-01
Expenditure
The Netherlands Red Cross
International NGO
14,494
EUR
2018-10-01
Expenditure
The Netherlands Red Cross
International NGO
8,501
EUR
2018-11-01
Expenditure
The Netherlands Red Cross
International NGO
11,969
EUR
2018-12-01
Expenditure
The Netherlands Red Cross
International NGO
12,821
EUR
2018-12-31
Expenditure
The Netherlands Red Cross
International NGO
1,647
EUR
2019-01-01
Expenditure
The Netherlands Red Cross
International NGO
6,966
EUR
2019-02-01
Expenditure
The Netherlands Red Cross
International NGO
12,457
EUR
2019-03-01
Expenditure
The Netherlands Red Cross
International NGO
9,996
EUR
2019-04-01
Expenditure
The Netherlands Red Cross
International NGO
7,510
EUR
2019-05-01
Expenditure
The Netherlands Red Cross
International NGO
9,481
EUR
2019-06-01
Expenditure
The Netherlands Red Cross
International NGO
9,858
EUR
2019-07-01
Expenditure
The Netherlands Red Cross
International NGO
7,404
EUR
2019-08-01
Expenditure
The Netherlands Red Cross
International NGO
2,798
EUR
2019-09-01
Expenditure
The Netherlands Red Cross
International NGO
3,400
EUR
2019-10-01
Expenditure
The Netherlands Red Cross
International NGO
3,602
EUR
2019-11-01
Expenditure
The Netherlands Red Cross
International NGO
4,818
EUR
2019-12-01
Expenditure
The Netherlands Red Cross
International NGO
9,306
EUR
2020-01-01
Expenditure
The Netherlands Red Cross
International NGO
7,445
EUR
2020-02-01
Expenditure
The Netherlands Red Cross
International NGO
6,340
EUR
2020-03-01
Expenditure
The Netherlands Red Cross
International NGO
6,073
EUR
2020-04-01
Expenditure
The Netherlands Red Cross
International NGO
9,611
EUR
2020-05-01
Expenditure
The Netherlands Red Cross
International NGO
4,858
EUR
2020-06-01
Expenditure
The Netherlands Red Cross
International NGO
12,979
EUR
2020-07-01
Expenditure
The Netherlands Red Cross
International NGO
7,362
EUR
2020-08-01
Expenditure
The Netherlands Red Cross
International NGO
5,536
EUR
2020-09-01
Expenditure
The Netherlands Red Cross
International NGO
4,047
EUR
2020-10-01
Expenditure
The Netherlands Red Cross
International NGO
9,604
EUR
2020-11-01
Expenditure
The Netherlands Red Cross
International NGO
4,532
EUR
2020-12-01
Expenditure
The Netherlands Red Cross
International NGO
7,407
EUR
2020-12-31
Expenditure
The Netherlands Red Cross
International NGO
-2,471
EUR
Expenditure
result( 6 )
outcome( 5 )
impact( 1 )
GLOSSARY
OutcomeResults of the activity that produce an effect on the overall communities or issues you serve. For example lower rate of infection after a vaccination programme.
ImpactThe long term effects of the outcomes, that lead to larger, over arching results, such as improved life-expectancy.
Outcome
indicator( 3 )
- Contribute to the development of local policies and mechanisms that secure the access of vulnerable groups to land
INDICATOR
Level of inclusion of Integrated Risk Management principles in development policies (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
0
N/A
2017-07-20 : 2018-07-05
Baseline comment
Key stakeholders are actively engaged in IRM mainstreaming in policies and legal frameworks
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
4
N/A
2018-07-05 : 2019-07-16
Baseline comment
Key stakeholders are actively engaged in IRM mainstreaming in policies and legal frameworks
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
4
N/A
2019-07-16 : 2019-07-16
Baseline comment
Key stakeholders are actively engaged in IRM mainstreaming in policies and legal frameworks
INDICATOR
Level of inclusion of Integrated Risk Management principles in investments (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
0
N/A
2017-07-20 : 2018-07-05
Baseline comment
Key stakeholders have concrete (signed) plans for IRM (proof) investments
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
2
N/A
2018-07-05 : 2019-07-16
Baseline comment
Key stakeholders have concrete (signed) plans for IRM (proof) investments
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
2
N/A
2019-07-16 : 2019-07-16
Baseline comment
Key stakeholders have concrete (signed) plans for IRM (proof) investments
INDICATOR
Level of inclusion of Integrated Risk Management principles in project and programme implementation (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
0
N/A
2017-07-24 : 2018-07-05
Baseline comment
Key stakeholders have started to implement IRM principles in their projects and practices
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
4
N/A
2018-07-05 : 2019-07-16
Baseline comment
Key stakeholders have started to implement IRM principles in their projects and practices
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
4
N/A
2019-07-16 : 2019-07-16
Baseline comment
Key stakeholders have started to implement IRM principles in their projects and practices
Outcome
indicator( 3 )
- Develop PDSECs (local development plans) that include a contingency plan that is financed
INDICATOR
Level of inclusion of Integrated Risk Management principles in development policies (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
2
4
Not provided
N/A
2015-12-31 : 2021-01-30
Baseline comment
Key stakeholders are open to implement IRM principles in their projects and practices
No dimension has been provided
No location has been provided
2016
2
Not provided
0
N/A
2017-07-24 : 2018-07-05
Baseline comment
Key stakeholders are open to implement IRM principles in their projects and practices
No dimension has been provided
No location has been provided
2016
2
Not provided
4
N/A
2018-07-05 : 2021-03-24
Baseline comment
Key stakeholders are open to implement IRM principles in their projects and practices
No dimension has been provided
No location has been provided
2016
2
Not provided
4
N/A
2021-03-24 : 2021-03-24
Baseline comment
Key stakeholders are open to implement IRM principles in their projects and practices
INDICATOR
Level of inclusion of Integrated Risk Management principles in development policies (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
2
4
Not provided
N/A
2015-12-31 : 2021-01-30
Baseline comment
Key stakeholders are open to support IRM (proof) investments
No dimension has been provided
No location has been provided
2016
2
Not provided
0
N/A
2017-07-20 : 2018-07-05
Baseline comment
Key stakeholders are open to support IRM (proof) investments
No dimension has been provided
No location has been provided
2016
2
Not provided
2
N/A
2018-07-05 : 2021-03-24
Baseline comment
Key stakeholders are open to support IRM (proof) investments
No dimension has been provided
No location has been provided
2016
2
Not provided
2
N/A
2021-03-24 : 2021-03-24
Baseline comment
Key stakeholders are open to support IRM (proof) investments
Actual comment
Investments
INDICATOR
Level of inclusion of Integrated Risk Management principles in development policies (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
2
4
Not provided
N/A
2015-12-31 : 2021-01-30
Baseline comment
Key stakeholders are open to supporting IRM mainstreaming in policies and legal frameworks
No dimension has been provided
No location has been provided
2016
2
Not provided
0
N/A
2017-07-20 : 2018-07-05
Baseline comment
Key stakeholders are open to supporting IRM mainstreaming in policies and legal frameworks
No dimension has been provided
No location has been provided
2016
2
Not provided
4
N/A
2018-07-05 : 2021-03-24
Baseline comment
Key stakeholders are open to supporting IRM mainstreaming in policies and legal frameworks
No dimension has been provided
No location has been provided
2016
2
Not provided
4
N/A
2021-03-24 : 2021-03-24
Baseline comment
Key stakeholders are open to supporting IRM mainstreaming in policies and legal frameworks
Actual comment
Practice
Outcome
indicator( 3 )
- Promote equitable management of water resources with a focus on maintaining the ecosystem services of wetlands in river basins
Promote the equitable management of water resources that keep vulnerable groups such as migrants (fishermen and herders) safe from the risks of natural disasters and the effects of hydro-agricultural development while maintaining the ecosystem services of wetlands in river basins
INDICATOR
Level of inclusion of Integrated Risk Management principles in development policies (0-5)
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
INDICATOR
Level of inclusion of Integrated Risk Management principles in investments (0-5)
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
INDICATOR
Level of inclusion of Integrated Risk Management principles in project and programme implementation (0-5)
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
Outcome
indicator( 3 )
- Promote sound & equal water resources management
Promote sound & equal water resources management that secures vulnerable groups, including fishermen, against the risk of natural disasters and the effects of irrigation schemes, maintaining ecosystem services of wetlands in river basins
INDICATOR
Level of inclusion of Integrated Risk Management principles in development policies (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
0
N/A
2017-07-20 : 2018-07-05
Baseline comment
Key stakeholders are open to support IRM (proof) investments
INDICATOR
Level of inclusion of Integrated Risk Management principles in development policies (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
0
N/A
2017-07-20 : 2018-07-05
Baseline comment
Key stakeholders are open to supporting IRM mainstreaming in policies and legal frameworks
INDICATOR
Level of inclusion of Integrated Risk Management principles in project and programme implementation (0-5)
REFERENCE
VOCAB Reporting Organisation 99
CODE PFR-ID01
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2016
Not provided
Not provided
0
N/A
2017-07-24 : 2018-07-05
Baseline comment
Key stakeholders are open to implement IRM principles in their projects and practices
Outcome
indicator( 3 )
Z (inactive) - Contribute to the implementation of the ECOWAS DRR Strategy through developing and implementing a cross-border contingency plan for Mali, Guinea and Burkina Faso
INDICATOR
Level of inclusion of Integrated Risk Management principles in development policies (0-5)
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
INDICATOR
Level of inclusion of Integrated Risk Management principles in investments (0-5)
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
INDICATOR
Level of inclusion of Integrated Risk Management principles in project and programme implementation (0-5)
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
Impact
indicator( 1 )
Other - People reached
INDICATOR
People living in communities benefitting from resilience interventions
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
General Enquiries
The Netherlands Red Cross
PU (Partnership Unit)
070 - 44 55 678
Postbus 28120, 2502 KC Den Haag, Netherlands