ACTIVITY TITLE
Capacity Building in the Field of Meteorology
Ilmatieteen laitos / Meteorologian alan yhteistyö
Reported by
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Bilateral 1
Project-type interventions C01
Standard grant 110 ODA 10 Untied 1
Planned start date 2021-01-01
Planned end date 2021-12-31
Actual start date 2021-01-01
activity status: Implementation
The activity is currently being implemented
WHO'S INVOLVED ( 2 )
PARTICIPATING ORG REFERENCE ROLE TYPE
Finnish Meteorological Institute
Ilmatieteen laitos
REF 51000-12
CRS University, college or other teaching institution, research institute or think-tank
Extending Foundation
Ministry for Foreign Affairs of Finland
REF FI-3
Funding Government
General
Ilmatieteen laitoksen toteuttama meteorologian alan IKI-hanke Uzbekistanin kansallisen laitoksen Uzhydrometin kanssa vuosina 2022-2025. Hankkeessa on tarkoitus vahvistaa Uzhydrometin kapasiteettia ja modernisoida alaa sekä kouluttaa henkilöstöä. Uzhyd rometin kapasiteetin vahvistamisella pyritään parempaan luonnonkatastrofien ennakointiin sekä parempaan tiedon saatavuuteen. Hanke edistää ilmastonmuutokseen sopeutumista ja ilmastokestävyyttä. Hankkeen budjetti on 2 000 000 euroa.
The Finnish Meteorolgical Institute will implement a project with the national institute of Uzbekistan Uzhydromet during the years 2022 -2025. In the project the capacity of Uzhydromet will be strengthened and modernized and the staff will be trained. Uz hydrome?s capacity will be strengthened to better anticipate natural disasters and to improve the availability of the information services. The project promotes adapting to climate change and climate sustainability. The budget of the project is EUR 2 000 000.
tag( 3 )
DESCRIPTION CODE VOCABULARY
Country-specific and regional development cooperation
Maa-ja aluekohtainen kehitysyhteistyö
Country-specific and regional development cooperation
Maa-ja aluekohtainen kehitysyhteistyö
2430662 Reporting Organisation
Human rights sensitive
Ihmisoikeudet huomioiva
Human rights sensitive
Ihmisoikeudet huomioiva
2 Reporting Organisation
Improving food security, access to water and sustainability is the main priority area in this act ivity
Improving food security, access to water and sustainability is the main priority area in this act ivity
PRIORITY AREA 4, PRIMARY Reporting Organisation
policy marker( 8 )
CODELIST SIGNIFICANCE VOCABULARY DESCRIPTION
Aid Targeting the Objectives of the Convention on Biological Diversity not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Aid Targeting the Objectives of the Convention to Combat Desertification not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Aid Targeting the Objectives of the Framework Convention on Climate Change - Adaptation principal objective OECD DAC CRS Principal (primary) policy objectives are those which can be identified as being fundamental in the design and impact of the activity and which are an explicit objective of the activity. They may be selected by answering the question "Would the activity have been undertaken without this objective?"
Aid Targeting the Objectives of the Framework Convention on Climate Change - Mitigation not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Aid to Environment principal objective OECD DAC CRS Principal (primary) policy objectives are those which can be identified as being fundamental in the design and impact of the activity and which are an explicit objective of the activity. They may be selected by answering the question "Would the activity have been undertaken without this objective?"
Gender Equality not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Participatory Development/Good Governance not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
Trade Development not targeted OECD DAC CRS The score "not targeted" means that the activity was examined but found not to target the policy objective.
recipient country ( 1 )
UzbekistanUZ
100
sector ( 1 )
OECD DAC CRS 5 digit1( 1 )
The sector reported corresponds to an OECD DAC CRS 5-digit purpose code http://reference.iatistandard.org/codelists/Sector/
Meteorological services15143
100
GLOSSARY
Meteorological servicesOperation or support of institutions dealing with weather forecasting.
Financial Overview
Outgoing Commitment ( 1 )
Budget ( 4 )
Outgoing Commitment
Budget
Budget ( 4 )
START END TYPE STATUS VALUE
2021-01-01 2021-12-31 Indicative 364,000
EUR
2022-01-01 2022-12-31 Indicative 636,000
EUR
2023-01-01 2023-12-31 Indicative 500,000
EUR
2024-01-01 2024-12-31 Indicative 500,000
EUR
Budget
Transactions ( 1 )
Outgoing Commitment ( 1 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2021-12-01
2,000,000
EUR
Outgoing Commitment