ACTIVITY TITLE
Comoros Interisland Connectivity Project SOP2
Reported by
World Bank 44000 Multilateral
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Multilateral (inflows) 2
Project-type interventions C01
Untied 1
DOCUMENTS ( 14 )
Environmental and Social Commitment Plan APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Environmental and Social Commitment Plan APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Environmental and Social Management Plan APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Environmental and Social Review Summary APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Environmental and Social Review Summary APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Environmental and Social Review Summary APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Project Appraisal Document APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Project Appraisal Document APPLICATION/PDF Pre- and post-project impact appraisal Objectives / Purpose of activity Intended ultimate beneficiaries Budget Project Information Document APPLICATION/PDF Objectives / Purpose of activity Intended ultimate beneficiaries Budget Financing Agreement APPLICATION/PDF Objectives / Purpose of activity Conditions Budget Summary information about contract Memorandum of understanding (If agreed by all parties) Implementation Status and Results Report APPLICATION/PDF Review of project performance and evaluation Results, outcomes and outputs Procurement Notices TEXT/HTML Tender Contract Awards TEXT/HTML Contract Project URL TEXT/HTML Activity web page
Planned start date 2024-03-20
Planned end date 2029-06-29
Actual start date 2024-03-20
Actual end date 2029-06-29
activity status: Implementation
The activity is currently being implemented
WHO'S INVOLVED ( 4 )
PARTICIPATING ORG REFERENCE ROLE TYPE
International Development Association
REF 44002
Funding Multilateral
International Development Association
REF 44002
Extending Multilateral
Ministry of Maritime and Air Transport
Implementing
The Union of Comoros
Accountable
Objectives
The Project Development Objective (PDO) is to improve maritime transport resilience, connectivity and safety between the islands.
General
The development objective of the Comoros - Interisland Connectivity Project SOP2 is to improve maritime transport resilience, connectivity and safety between the islands. The project will consist of the following components: Component 1. Improvement of Climate Resilience and Capacity of Port Infrastructure (US$28 million from AfDB and US$5 million from IsDB); Component 2. Maritime safety and safe passenger boat program (US$3 million IDA equivalent; US$10 million from IsDB); Component 3. Implementation support and capacity building (US$2 million IDA equivalent); and Component 4: Contingent emergency response (US$0 million).
humanitarian scope ( 2 )
TITLE CODE VOCABULARY TYPE
EP-2020-000012-001 Glide Emergency
HCOVD20 Humanitarian Plan Appeal
recipient country ( 1 )
Comoros (the)KM
100
LOCATION ( 1 )
NAME DESCRIPTION POSITION CLASS REACH EXACTNESS
Moroni
ID 921772 (Geonames)
-11.70216 43.255058 Populated Place Activity Approximate
sector ( 17 )
Reporting Organisation99( 2 )
The sector reported corresponds to a sector vocabulary maintained by the reporting organisation for this activity
FY17 - Ports/Waterways TP
60
FY17 - Public Administration - Transportation TF
40
Reporting Organisation 298( 15 )
The sector reported corresponds to a sector vocabulary maintained by the reporting organisation for this activity (if they are referencing more than one)
Adaptation 000812
0
Climate change 000081
0
Coastal Zone Management 000836
0
Disaster Risk Management 000075
0
Disease Control 000062
0
Flood and Drought Risk Management 000754
0
Gender 000061
0
Pandemic Response 000626
0
Public Private Partnerships 000023
0
Public Transport 000713
0
Renewable Natural Resources Asset Management 000083
0
Road Safety 000074
0
Trade Logistics 000142
0
Trade 000014
0
Urban Development 000071
0
capital spend
The percentage of the total commitment that is for capital spending
100
Financial Overview
Outgoing Commitment ( 1 )
Budget ( 154 )
Outgoing Commitment
Budget
Budget ( 154 )
START END TYPE STATUS VALUE
2023-02-01 2023-02-28 Original Indicative 0
USD
2023-02-01 2023-02-28 Revised Indicative 0
USD
2023-03-01 2023-03-31 Original Indicative 0
USD
2023-03-01 2023-03-31 Revised Indicative 0
USD
2023-04-01 2023-04-30 Original Indicative 0
USD
2023-04-01 2023-04-30 Revised Indicative 0
USD
2023-05-01 2023-05-31 Original Indicative 0
USD
2023-05-01 2023-05-31 Revised Indicative 0
USD
2023-06-01 2023-06-30 Original Indicative 0
USD
2023-06-01 2023-06-30 Revised Indicative 0
USD
2023-07-01 2023-07-31 Original Indicative 0
USD
2023-07-01 2023-07-31 Revised Indicative 0
USD
2023-08-01 2023-08-31 Original Indicative 0
USD
2023-08-01 2023-08-31 Revised Indicative 0
USD
2023-09-01 2023-09-30 Original Indicative 0
USD
2023-09-01 2023-09-30 Revised Indicative 0
USD
2023-10-01 2023-10-31 Original Indicative 0
USD
2023-10-01 2023-10-31 Revised Indicative 0
USD
2023-11-01 2023-11-30 Original Indicative 330,000
USD
2023-11-01 2023-11-30 Revised Indicative 330,000
USD
2023-12-01 2023-12-31 Original Indicative 230,000
USD
2023-12-01 2023-12-31 Revised Indicative 230,000
USD
2024-01-01 2024-01-31 Original Indicative 470,000
USD
2024-01-01 2024-01-31 Revised Indicative 470,000
USD
2024-02-01 2024-02-29 Original Indicative 240,000
USD
2024-02-01 2024-02-29 Revised Indicative 240,000
USD
2024-03-01 2024-03-31 Original Indicative 470,000
USD
2024-03-01 2024-03-31 Revised Indicative 470,000
USD
2024-04-01 2024-04-30 Original Indicative 240,000
USD
2024-04-01 2024-04-30 Revised Indicative 240,000
USD
2024-05-01 2024-05-31 Original Indicative 240,000
USD
2024-05-01 2024-05-31 Revised Indicative 240,000
USD
2024-06-01 2024-06-30 Original Indicative 470,000
USD
2024-06-01 2024-06-30 Revised Indicative 470,000
USD
2024-07-01 2024-07-31 Original Indicative 240,000
USD
2024-07-01 2024-07-31 Revised Indicative 240,000
USD
2024-08-01 2024-08-31 Original Indicative 470,000
USD
2024-08-01 2024-08-31 Revised Indicative 470,000
USD
2024-09-01 2024-09-30 Original Indicative 240,000
USD
2024-09-01 2024-09-30 Revised Indicative 240,000
USD
2024-10-01 2024-10-31 Original Indicative 480,000
USD
2024-10-01 2024-10-31 Revised Indicative 480,000
USD
2024-11-01 2024-11-30 Original Indicative 240,000
USD
2024-11-01 2024-11-30 Revised Indicative 240,000
USD
2024-12-01 2024-12-31 Original Indicative 240,000
USD
2024-12-01 2024-12-31 Revised Indicative 240,000
USD
2025-01-01 2025-01-31 Original Indicative 480,000
USD
2025-01-01 2025-01-31 Revised Indicative 480,000
USD
2025-02-01 2025-02-28 Original Indicative 240,000
USD
2025-02-01 2025-02-28 Revised Indicative 240,000
USD
2025-03-01 2025-03-31 Original Indicative 480,000
USD
2025-03-01 2025-03-31 Revised Indicative 480,000
USD
2025-04-01 2025-04-30 Original Indicative 240,000
USD
2025-04-01 2025-04-30 Revised Indicative 240,000
USD
2025-05-01 2025-05-31 Original Indicative 480,000
USD
2025-05-01 2025-05-31 Revised Indicative 480,000
USD
2025-06-01 2025-06-30 Original Indicative 240,000
USD
2025-06-01 2025-06-30 Revised Indicative 240,000
USD
2025-07-01 2025-07-31 Original Indicative 240,000
USD
2025-07-01 2025-07-31 Revised Indicative 240,000
USD
2025-08-01 2025-08-31 Original Indicative 500,000
USD
2025-08-01 2025-08-31 Revised Indicative 500,000
USD
2025-09-01 2025-09-30 Original Indicative 270,000
USD
2025-09-01 2025-09-30 Revised Indicative 270,000
USD
2025-10-01 2025-10-31 Original Indicative 580,000
USD
2025-10-01 2025-10-31 Revised Indicative 580,000
USD
2025-11-01 2025-11-30 Original Indicative 300,000
USD
2025-11-01 2025-11-30 Revised Indicative 300,000
USD
2025-12-01 2025-12-31 Original Indicative 600,000
USD
2025-12-01 2025-12-31 Revised Indicative 600,000
USD
2026-01-01 2026-01-31 Original Indicative 300,000
USD
2026-01-01 2026-01-31 Revised Indicative 300,000
USD
2026-02-01 2026-02-28 Original Indicative 300,000
USD
2026-02-01 2026-02-28 Revised Indicative 300,000
USD
2026-03-01 2026-03-31 Original Indicative 610,000
USD
2026-03-01 2026-03-31 Revised Indicative 610,000
USD
2026-04-01 2026-04-30 Original Indicative 300,000
USD
2026-04-01 2026-04-30 Revised Indicative 300,000
USD
2026-05-01 2026-05-31 Original Indicative 600,000
USD
2026-05-01 2026-05-31 Revised Indicative 600,000
USD
2026-06-01 2026-06-30 Original Indicative 300,000
USD
2026-06-01 2026-06-30 Revised Indicative 300,000
USD
2026-07-01 2026-07-31 Original Indicative 620,000
USD
2026-07-01 2026-07-31 Revised Indicative 620,000
USD
2026-08-01 2026-08-31 Original Indicative 320,000
USD
2026-08-01 2026-08-31 Revised Indicative 320,000
USD
2026-09-01 2026-09-30 Original Indicative 330,000
USD
2026-09-01 2026-09-30 Revised Indicative 330,000
USD
2026-10-01 2026-10-31 Original Indicative 720,000
USD
2026-10-01 2026-10-31 Revised Indicative 720,000
USD
2026-11-01 2026-11-30 Original Indicative 400,000
USD
2026-11-01 2026-11-30 Revised Indicative 400,000
USD
2026-12-01 2026-12-31 Original Indicative 800,000
USD
2026-12-01 2026-12-31 Revised Indicative 800,000
USD
2027-01-01 2027-01-31 Original Indicative 380,000
USD
2027-01-01 2027-01-31 Revised Indicative 380,000
USD
2027-02-01 2027-02-28 Original Indicative 810,000
USD
2027-02-01 2027-02-28 Revised Indicative 810,000
USD
2027-03-01 2027-03-31 Original Indicative 430,000
USD
2027-03-01 2027-03-31 Revised Indicative 430,000
USD
2027-04-01 2027-04-30 Original Indicative 450,000
USD
2027-04-01 2027-04-30 Revised Indicative 450,000
USD
2027-05-01 2027-05-31 Original Indicative 970,000
USD
2027-05-01 2027-05-31 Revised Indicative 970,000
USD
2027-06-01 2027-06-30 Original Indicative 880,000
USD
2027-06-01 2027-06-30 Revised Indicative 880,000
USD
2027-07-01 2027-07-31 Original Indicative 1,760,000
USD
2027-07-01 2027-07-31 Revised Indicative 1,760,000
USD
2027-08-01 2027-08-31 Original Indicative 730,000
USD
2027-08-01 2027-08-31 Revised Indicative 730,000
USD
2027-09-01 2027-09-30 Original Indicative 1,290,000
USD
2027-09-01 2027-09-30 Revised Indicative 1,290,000
USD
2027-10-01 2027-10-31 Original Indicative 610,000
USD
2027-10-01 2027-10-31 Revised Indicative 610,000
USD
2027-11-01 2027-11-30 Original Indicative 590,000
USD
2027-11-01 2027-11-30 Revised Indicative 590,000
USD
2027-12-01 2027-12-31 Original Indicative 1,170,000
USD
2027-12-01 2027-12-31 Revised Indicative 1,170,000
USD
2028-01-01 2028-01-31 Original Indicative 580,000
USD
2028-01-01 2028-01-31 Revised Indicative 580,000
USD
2028-02-01 2028-02-29 Original Indicative 1,160,000
USD
2028-02-01 2028-02-29 Revised Indicative 1,160,000
USD
2028-03-01 2028-03-31 Original Indicative 580,000
USD
2028-03-01 2028-03-31 Revised Indicative 580,000
USD
2028-04-01 2028-04-30 Original Indicative 1,160,000
USD
2028-04-01 2028-04-30 Revised Indicative 1,160,000
USD
2028-05-01 2028-05-31 Original Indicative 580,000
USD
2028-05-01 2028-05-31 Revised Indicative 580,000
USD
2028-06-01 2028-06-30 Original Indicative 580,000
USD
2028-06-01 2028-06-30 Revised Indicative 580,000
USD
2028-07-01 2028-07-31 Original Indicative 1,160,000
USD
2028-07-01 2028-07-31 Revised Indicative 1,160,000
USD
2028-08-01 2028-08-31 Original Indicative 580,000
USD
2028-08-01 2028-08-31 Revised Indicative 580,000
USD
2028-09-01 2028-09-30 Original Indicative 1,170,000
USD
2028-09-01 2028-09-30 Revised Indicative 1,170,000
USD
2028-10-01 2028-10-31 Original Indicative 590,000
USD
2028-10-01 2028-10-31 Revised Indicative 590,000
USD
2028-11-01 2028-11-30 Original Indicative 1,180,000
USD
2028-11-01 2028-11-30 Revised Indicative 1,180,000
USD
2028-12-01 2028-12-31 Original Indicative 590,000
USD
2028-12-01 2028-12-31 Revised Indicative 590,000
USD
2029-01-01 2029-01-31 Original Indicative 1,770,000
USD
2029-01-01 2029-01-31 Revised Indicative 1,770,000
USD
2029-02-01 2029-02-28 Original Indicative 0
USD
2029-02-01 2029-02-28 Revised Indicative 0
USD
2029-03-01 2029-03-31 Original Indicative 590,000
USD
2029-03-01 2029-03-31 Revised Indicative 590,000
USD
2029-04-01 2029-04-30 Original Indicative 1,190,000
USD
2029-04-01 2029-04-30 Revised Indicative 1,190,000
USD
2029-05-01 2029-05-31 Original Indicative 1,620,000
USD
2029-05-01 2029-05-31 Revised Indicative 1,620,000
USD
2029-06-01 2029-06-30 Original Indicative 0
USD
2029-06-01 2029-06-30 Revised Indicative 0
USD
Budget
Transactions ( 1 )
Outgoing Commitment ( 1 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2024-03-31
Total Commitment in March Month of 2024
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
5,000,000
USD
Outgoing Commitment
result( 11 )
output( 7 )
outcome( 4 )
GLOSSARY
OutputResults of the activity that came about as a direct effect of your work and specific, what is done, and what communities are reached. For example, X number of individuals.
OutcomeResults of the activity that produce an effect on the overall communities or issues you serve. For example lower rate of infection after a vaccination programme.
Output
indicator( 1 )
Intermediate Results Indicator
INDICATOR
Number of domestic ferry passengers on an annual basis
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2022
31000
85000 31000
0%
2022-12-01 : 2029-06-01
Output
indicator( 1 )
Intermediate Results Indicator
INDICATOR
Establishment of a safety committee including female representatives
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2023
No
Yes No
N/A
2023-01-01 : 2029-06-01
Output
indicator( 1 )
Intermediate Results Indicator
INDICATOR
Number of safer passenger boats to be introduced under the pilot program
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2024
0
4 0.00
0%
2024-01-01 : 2028-06-30
Output
indicator( 1 )
Intermediate Results Indicator
INDICATOR
Number of secondary ports to be constructed
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2024
0
2 0.00
0%
2024-01-01 : 2029-06-01
Output
indicator( 1 )
Intermediate Results Indicator
INDICATOR
Percentage of complaints responded and/or resolved within the stipulated standard for response times
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
2024
0.00
75.00 0.00
0%
2024-01-01 : 2028-06-30
Output
indicator( 1 )
Intermediate Results Indicator
INDICATOR
Satisfaction rating by project beneficiaries
FACET BASELINE TARGET ACTUAL % PERIOD
Percentage Percentage
No dimension has been provided
No location has been provided
2024
0.00
75.00 0.00
0%
2024-01-01 : 2028-06-30
Output
indicator( 1 )
Intermediate Results Indicator
INDICATOR
Port Boingoma is rehabilitated and expanded with climate resilience design built in
FACET BASELINE TARGET ACTUAL % PERIOD
Qualitative Qualitative
No dimension has been provided
No location has been provided
2024
No
Yes No
N/A
2024-01-01 : 2029-06-01
Outcome
indicator( 1 )
Project Development Objectives
INDICATOR
Increased maritime connectivity in terms of volume of freight handled at climate resilient Port Boingoma
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2022
16000
50000 16000
0%
2022-12-01 : 2029-06-01
Outcome
indicator( 1 )
Project Development Objectives
INDICATOR
Number of people that benefit from improved access to sustainable transport infrastructure and services
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2023
0
65000 0
0%
2023-10-01 : 2029-06-01
Outcome
indicator( 1 )
Project Development Objectives
INDICATOR
Reduction in the number of days each year when Port Boingoma is nonoperational due to weather conditions
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2024
216
20 216
0%
2024-01-01 : 2029-06-01
Outcome
indicator( 1 )
Project Development Objectives
INDICATOR
Reduction in the number of maritime transport accidents on a yearly basis
FACET BASELINE TARGET ACTUAL % PERIOD
Unit Unit
No dimension has been provided
No location has been provided
2024
25
0 25
0%
2024-01-01 : 2028-06-30
General Enquiries
The World Bank
Atsushi Iimi
+1-202-473-1000
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
Project Management
Bd. de l'OcEan, Moroni, Comoros, +269 3357308, ministeretransportmaritime@gmail.com
conditions( - )
{_it./conditions/condition:/condition}
NARRATIVE TYPE DESCRIPTION