ACTIVITY TITLE
Tamil Nadu and Puducherry Coastal Disaster Risk Reduction Project
Reported by
World Bank 44000 Multilateral
ACTIVITY SCOPE COLLABORATION TYPE AID TYPE FINANCE TYPE FLOW TYPE TIED STATUS HIERARCHY
Multilateral (inflows) 2
Project-type interventions C01
Untied 1
Planned start date 2013-05-30
Planned end date 2020-06-30
Actual start date 2013-06-20
Actual end date 2020-06-30
activity status: Finalisation
Physical activity is complete or the final disbursement has been made, but the activity remains open pending financial sign off or M&E
WHO'S INVOLVED ( 6 )
PARTICIPATING ORG REFERENCE ROLE TYPE
Department of Economic Affairs, Ministry of Finance, Republic of India
Accountable
International Development Association
REF 44002
Funding Multilateral
International Development Association
REF 44002
Extending Multilateral
Project Implementation Agency, Department of Revenue and DM, Government of Puducherry
Implementing
Tamil Nadu Medical Services Corporation Limited
Implementing
Tamil Nadu State Disaster Management Agency, Government of Tamil Nadu
Implementing
Objectives
Increasing the resilience of coastal communities in Tamil Nadu and Puducherry, to a range of hydro-meteorological and geophysical hazards along with improving project implementing entities capacity to respond promptly and effectively to an eligible crisis or emergency.
General
The objective of the Tamil Nadu and Puducherry Coastal Disaster Risk Reduction Project for India is increasing the resilience of coastal communities in Tamil Nadu and Puducherry, to a range of hydrometeorological and geophysical hazards along with improving project implementation entities? capacity to respond promptly and effectively to an eligible crisis or emergency. The project has five components. The first component is vulnerability reduction. The objective of this component is to reduce the vulnerability of coastal communities through infrastructure such as permanent houses, evacuation shelters and routes, and resilient electrical networks. It has following three sub-components: (i) resilient housing; (ii) evacuation shelters, routes and early warning systems; and (iii) cyclone resilient electrical network. The second component is sustainable fisheries. The objective of this component is to address gaps in the context of a long term vision for the fisheries sector. The component aims at upgrading infrastructure, developing an approach for co-management of fisheries and addressing safety at sea. This component has following two sub-components: (a) fishing infrastructure; and (b) Second Fisheries Management for Sustainable Livelihood (FIMSUL II). The third component is capacity building in disaster risk management. This component will focus on strengthening the capacity of government institutions, civil society, the school education system and coastal communities through following four sub-components: (i) strengthening of state disaster management authority; (ii) Community Based Disaster Risk Management Program (CBDRM); (iii) curriculum development on disaster risk reduction for schools and training institutions; and (iv) completing preparation of the Integrated Coastal Zone Management (ICZM) plan for Tamil Nadu, completing erection of High Tide Line (HTL) pillars across all 13 coastal districts and stake holder training on coastal zone management. The fourth component is implementation support. This will include incremental operating costs, that of operating the Project Management Unit (PMU) and respective Project Implementation Units (PIUs) in the line departments. In addition, the component will include consultancies required for the preparation and supervision of specific activities, trainings, exposure visits and knowledge exchange programs. The fifth component is contingent emergency financing. This component will draw resources from the unallocated expenditure category and or allow the government of Tamil Nadu and or Puducherry to request the Bank to re-categorize and reallocate financing from other project components to partially cover emergency response and recovery costs.
recipient country ( 1 )
IndiaIN
100
LOCATION ( 2 )
NAME DESCRIPTION POSITION CLASS REACH EXACTNESS
State of Tamil Nadu
ID 0001255053 (Geonames)
11 78.333328 Administrative Region Activity Approximate
Union Territory of Puducherry
ID 0001259424 (Geonames)
11.93333 79.816673 Administrative Region Activity Approximate
sector ( 22 )
OECD DAC CRS 5 digit1( 6 )
The sector reported corresponds to an OECD DAC CRS 5-digit purpose code http://reference.iatistandard.org/codelists/Sector/
Electric power transmission and distribution (centralised grids)23630
26
Multi-hazard response preparedness74020
26
Fishing policy and administrative management31310
21
Housing policy and administrative management16030
20
Information services22013
6
National road construction21023
1
GLOSSARY
Electric power transmission and distribution (centralised grids)Grid distribution from power source to end user; transmission lines. Also includes storage of energy to generate power (e.g. pumped hydro, batteries) and the extension of grid access, often to rural areas.
Multi-hazard response preparednessBuilding the responsiveness, capability and capacity of international, regional and national humanitarian actors to disasters. Support to the institutional capacities of national and local government, specialised humanitarian bodies, and civil society organisations to anticipate, respond and recover from the impact of potential, imminent and current hazardous events and emergency situations that pose humanitarian threats and could call for a humanitarian response. This includes risk analysis and assessment, mitigation, preparedness, such as stockpiling of emergency items and training and capacity building aimed to increase the speed and effectiveness of lifesaving assistance delivered in the occurrence of crisis.
Fishing policy and administrative managementFishing sector policy, planning and programmes; institution capacity building and advice; ocean and coastal fishing; marine and freshwater fish surveys and prospecting; fishing boats/equipment; unspecified fishing activities.
Housing policy and administrative managementHousing sector policy, planning and programmes; excluding low-cost housing and slum clearance (16040).
Information servicesProvision of information services.
National road constructionConstruction or operation of national road transport systems and facilities.
Reporting Organisation99( 7 )
The sector reported corresponds to a sector vocabulary maintained by the reporting organisation for this activity
FY17 - Fisheries AF
24
FY17 - Social Protection SA
20
FY17 - Housing Construction YH
19
FY17 - Other Water Supply, Sanitation and Waste Management WZ
19
FY17 - Sub-National Government BH
8
FY17 - Other Public Administration BZ
5
FY17 - Other Transportation TZ
5
Reporting Organisation 298( 9 )
The sector reported corresponds to a sector vocabulary maintained by the reporting organisation for this activity (if they are referencing more than one)
Disaster Risk Management 000075
51
Rural Development 000072
34
Rural Infrastructure and service delivery 000723
29
Disaster Preparedness 000753
17
Disaster Response and Recovery 000751
17
Disaster Risk Finance 000331
17
Disaster Risk Reduction 000752
17
Finance for Development 000033
17
Rural Non-farm Income Generation 000722
5
capital spend
The percentage of the total commitment that is for capital spending
100
Financial Overview
Outgoing Commitment ( 3 )
Disbursement ( 40 )
Interest Payment ( 22 )
Loan Repayment ( 13 )
Budget ( 194 )
Outgoing Commitment
Disbursement
Interest Payment
Loan Repayment
Budget
Budget ( 194 )
START END TYPE STATUS VALUE
2013-06-01 2013-06-30 Original Indicative 0
USD
2013-06-01 2013-06-30 Revised Indicative 0
USD
2013-07-01 2013-07-31 Original Indicative 0
USD
2013-07-01 2013-07-31 Revised Indicative 4,514,672.66
USD
2013-08-01 2013-08-31 Original Indicative 0
USD
2013-08-01 2013-08-31 Revised Indicative 4,514,672.66
USD
2013-09-01 2013-09-30 Original Indicative 0
USD
2013-09-01 2013-09-30 Revised Indicative 4,514,672.66
USD
2013-10-01 2013-10-31 Original Indicative 0
USD
2013-10-01 2013-10-31 Revised Indicative 4,514,672.66
USD
2013-11-01 2013-11-30 Original Indicative 0
USD
2013-11-01 2013-11-30 Revised Indicative 4,514,672.66
USD
2013-12-01 2013-12-31 Original Indicative 0
USD
2013-12-01 2013-12-31 Revised Indicative 4,514,672.66
USD
2014-01-01 2014-01-31 Original Indicative 0
USD
2014-01-01 2014-01-31 Revised Indicative 4,514,672.66
USD
2014-02-01 2014-02-28 Original Indicative 0
USD
2014-02-01 2014-02-28 Revised Indicative 4,514,672.66
USD
2014-03-01 2014-03-31 Original Indicative 0
USD
2014-03-01 2014-03-31 Revised Indicative 4,514,672.66
USD
2014-04-01 2014-04-30 Original Indicative 30,000,000
USD
2014-04-01 2014-04-30 Revised Indicative 4,514,672.66
USD
2014-05-01 2014-05-31 Original Indicative 30,000,000
USD
2014-05-01 2014-05-31 Revised Indicative 4,514,672.66
USD
2014-06-01 2014-06-30 Original Indicative 30,000,000
USD
2014-06-01 2014-06-30 Revised Indicative 4,514,672.68
USD
2014-07-01 2014-07-31 Original Indicative 1,666,666.67
USD
2014-07-01 2014-07-31 Revised Indicative 2,067,607.61
USD
2014-08-01 2014-08-31 Original Indicative 1,666,666.67
USD
2014-08-01 2014-08-31 Revised Indicative 2,067,607.61
USD
2014-09-01 2014-09-30 Original Indicative 1,666,666.66
USD
2014-09-01 2014-09-30 Revised Indicative 2,067,607.61
USD
2014-10-01 2014-10-31 Original Indicative 1,666,666.67
USD
2014-10-01 2014-10-31 Revised Indicative 2,067,607.61
USD
2014-11-01 2014-11-30 Original Indicative 1,666,666.67
USD
2014-11-01 2014-11-30 Revised Indicative 2,067,607.61
USD
2014-12-01 2014-12-31 Original Indicative 1,666,666.66
USD
2014-12-01 2014-12-31 Revised Indicative 2,067,607.61
USD
2015-01-01 2015-01-31 Original Indicative 1,666,666.67
USD
2015-01-01 2015-01-31 Revised Indicative 2,067,607.61
USD
2015-02-01 2015-02-28 Original Indicative 1,666,666.67
USD
2015-02-01 2015-02-28 Revised Indicative 2,067,607.61
USD
2015-03-01 2015-03-31 Original Indicative 1,666,666.66
USD
2015-03-01 2015-03-31 Revised Indicative 2,067,607.61
USD
2015-04-01 2015-04-30 Original Indicative 1,666,666.67
USD
2015-04-01 2015-04-30 Revised Indicative 2,067,607.61
USD
2015-05-01 2015-05-31 Original Indicative 1,666,666.67
USD
2015-05-01 2015-05-31 Revised Indicative 2,067,607.61
USD
2015-06-01 2015-06-30 Original Indicative 1,666,666.66
USD
2015-06-01 2015-06-30 Revised Indicative 2,067,607.59
USD
2015-07-01 2015-07-31 Revised Indicative 1,032,771.85
USD
2015-07-01 2015-07-31 Original Indicative 2,500,000.01
USD
2015-08-01 2015-08-31 Revised Indicative 1,032,771.85
USD
2015-08-01 2015-08-31 Original Indicative 2,500,000.01
USD
2015-09-01 2015-09-30 Revised Indicative 1,032,771.85
USD
2015-09-01 2015-09-30 Original Indicative 2,500,000.01
USD
2015-10-01 2015-10-31 Revised Indicative 1,032,771.85
USD
2015-10-01 2015-10-31 Original Indicative 2,500,000.01
USD
2015-11-01 2015-11-30 Revised Indicative 1,032,771.85
USD
2015-11-01 2015-11-30 Original Indicative 2,500,000.01
USD
2015-12-01 2015-12-31 Revised Indicative 1,032,771.85
USD
2015-12-01 2015-12-31 Original Indicative 2,500,000.01
USD
2016-01-01 2016-01-31 Revised Indicative 1,032,771.85
USD
2016-01-01 2016-01-31 Original Indicative 3,333,333.33
USD
2016-02-01 2016-02-29 Revised Indicative 1,032,771.85
USD
2016-02-01 2016-02-29 Original Indicative 3,333,333.33
USD
2016-03-01 2016-03-31 Revised Indicative 1,032,771.85
USD
2016-03-01 2016-03-31 Original Indicative 3,333,333.34
USD
2016-04-01 2016-04-30 Revised Indicative 1,032,771.85
USD
2016-04-01 2016-04-30 Original Indicative 3,333,333.33
USD
2016-05-01 2016-05-31 Revised Indicative 1,032,771.85
USD
2016-05-01 2016-05-31 Original Indicative 3,333,333.33
USD
2016-06-01 2016-06-30 Revised Indicative 1,032,771.8
USD
2016-06-01 2016-06-30 Original Indicative 3,333,333.34
USD
2016-07-01 2016-07-31 Revised Indicative 1,593,399.78
USD
2016-07-01 2016-07-31 Original Indicative 4,000,000
USD
2016-08-01 2016-08-31 Revised Indicative 1,593,399.78
USD
2016-08-01 2016-08-31 Original Indicative 4,000,000
USD
2016-09-01 2016-09-30 Revised Indicative 1,593,399.78
USD
2016-09-01 2016-09-30 Original Indicative 4,000,000
USD
2016-10-01 2016-10-31 Revised Indicative 1,593,399.78
USD
2016-10-01 2016-10-31 Original Indicative 4,000,000
USD
2016-11-01 2016-11-30 Revised Indicative 1,593,399.78
USD
2016-11-01 2016-11-30 Original Indicative 4,000,000
USD
2016-12-01 2016-12-31 Revised Indicative 1,593,399.78
USD
2016-12-01 2016-12-31 Original Indicative 4,000,000
USD
2017-01-01 2017-01-31 Revised Indicative 1,593,399.78
USD
2017-01-01 2017-01-31 Original Indicative 3,333,333.33
USD
2017-02-01 2017-02-28 Revised Indicative 1,593,399.78
USD
2017-02-01 2017-02-28 Original Indicative 3,333,333.33
USD
2017-03-01 2017-03-31 Revised Indicative 1,593,399.78
USD
2017-03-01 2017-03-31 Original Indicative 3,333,333.34
USD
2017-04-01 2017-04-30 Revised Indicative 1,593,399.78
USD
2017-04-01 2017-04-30 Original Indicative 3,666,666.67
USD
2017-05-01 2017-05-31 Revised Indicative 1,593,399.78
USD
2017-05-01 2017-05-31 Original Indicative 3,666,666.67
USD
2017-06-01 2017-06-30 Revised Indicative 1,593,399.81
USD
2017-06-01 2017-06-30 Original Indicative 3,666,666.66
USD
2017-07-01 2017-07-31 Original Indicative 3,333,333.33
USD
2017-07-01 2017-07-31 Revised Indicative 932,767.43
USD
2017-08-01 2017-08-31 Original Indicative 3,333,333.33
USD
2017-08-01 2017-08-31 Revised Indicative 932,767.43
USD
2017-09-01 2017-09-30 Original Indicative 3,333,333.34
USD
2017-09-01 2017-09-30 Revised Indicative 932,767.43
USD
2017-10-01 2017-10-31 Original Indicative 3,333,333.33
USD
2017-10-01 2017-10-31 Revised Indicative 932,767.43
USD
2017-11-01 2017-11-30 Original Indicative 3,333,333.33
USD
2017-11-01 2017-11-30 Revised Indicative 932,767.43
USD
2017-12-01 2017-12-31 Original Indicative 3,333,333.34
USD
2017-12-01 2017-12-31 Revised Indicative 932,767.43
USD
2018-01-01 2018-01-31 Original Indicative 3,333,333.33
USD
2018-01-01 2018-01-31 Revised Indicative 932,767.43
USD
2018-02-01 2018-02-28 Original Indicative 3,333,333.33
USD
2018-02-01 2018-02-28 Revised Indicative 932,767.43
USD
2018-03-01 2018-03-31 Original Indicative 3,333,333.34
USD
2018-03-01 2018-03-31 Revised Indicative 932,767.43
USD
2018-04-01 2018-04-30 Original Indicative 3,333,333.33
USD
2018-04-01 2018-04-30 Revised Indicative 932,767.43
USD
2018-05-01 2018-05-31 Original Indicative 3,333,333.33
USD
2018-05-01 2018-05-31 Revised Indicative 932,767.43
USD
2018-06-01 2018-06-30 Original Indicative 3,333,333.34
USD
2018-06-01 2018-06-30 Revised Indicative 932,767.47
USD
2018-07-01 2018-07-31 Original Indicative 1,430,109.3
USD
2018-07-01 2018-07-31 Revised Indicative 1,440,684.96
USD
2018-08-01 2018-08-31 Original Indicative 1,430,109.3
USD
2018-08-01 2018-08-31 Revised Indicative 1,440,684.96
USD
2018-09-01 2018-09-30 Original Indicative 1,430,109.29
USD
2018-09-01 2018-09-30 Revised Indicative 1,440,684.96
USD
2018-10-01 2018-10-31 Original Indicative 0
USD
2018-10-01 2018-10-31 Revised Indicative 1,440,684.96
USD
2018-11-01 2018-11-30 Original Indicative 0
USD
2018-11-01 2018-11-30 Revised Indicative 1,440,684.96
USD
2018-12-01 2018-12-31 Original Indicative 0
USD
2018-12-01 2018-12-31 Revised Indicative 1,440,684.96
USD
2019-01-01 2019-01-31 Original Indicative 0
USD
2019-01-01 2019-01-31 Revised Indicative 1,440,684.96
USD
2019-02-01 2019-02-28 Original Indicative 0
USD
2019-02-01 2019-02-28 Revised Indicative 1,440,684.96
USD
2019-03-01 2019-03-31 Original Indicative 0
USD
2019-03-01 2019-03-31 Revised Indicative 1,440,684.96
USD
2019-04-01 2019-04-30 Original Indicative 0
USD
2019-04-01 2019-04-30 Revised Indicative 1,440,684.96
USD
2019-05-01 2019-05-31 Original Indicative 0
USD
2019-05-01 2019-05-31 Revised Indicative 1,440,684.96
USD
2019-06-01 2019-06-30 Original Indicative 0
USD
2019-06-01 2019-06-30 Revised Indicative 1,440,684.97
USD
2019-07-01 2019-07-31 Original Indicative 0
USD
2019-07-01 2019-07-31 Revised Indicative 1,027,631.79
USD
2019-08-01 2019-08-31 Original Indicative 0
USD
2019-08-01 2019-08-31 Revised Indicative 1,027,631.79
USD
2019-09-01 2019-09-30 Original Indicative 0
USD
2019-09-01 2019-09-30 Revised Indicative 1,027,631.79
USD
2019-10-01 2019-10-31 Original Indicative 0
USD
2019-10-01 2019-10-31 Revised Indicative 1,027,631.79
USD
2019-11-01 2019-11-30 Original Indicative 0
USD
2019-11-01 2019-11-30 Revised Indicative 1,027,631.79
USD
2019-12-01 2019-12-31 Original Indicative 0
USD
2019-12-01 2019-12-31 Revised Indicative 1,027,631.79
USD
2020-01-01 2020-01-31 Original Indicative 0
USD
2020-01-01 2020-01-31 Revised Indicative 1,027,631.79
USD
2020-02-01 2020-02-29 Original Indicative 0
USD
2020-02-01 2020-02-29 Revised Indicative 1,027,631.79
USD
2020-03-01 2020-03-31 Original Indicative 0
USD
2020-03-01 2020-03-31 Revised Indicative 1,027,631.79
USD
2020-04-01 2020-04-30 Original Indicative 0
USD
2020-04-01 2020-04-30 Revised Indicative 1,027,631.79
USD
2020-05-01 2020-05-31 Original Indicative 0
USD
2020-05-01 2020-05-31 Revised Indicative 1,027,631.79
USD
2020-06-01 2020-06-30 Original Indicative 0
USD
2020-06-01 2020-06-30 Revised Indicative 1,027,631.75
USD
2020-07-01 2020-07-31 Original Indicative 0
USD
2020-07-01 2020-07-31 Revised Indicative 4,890,833.33
USD
2020-08-01 2020-08-31 Original Indicative 0
USD
2020-08-01 2020-08-31 Revised Indicative 4,890,833.33
USD
2020-09-01 2020-09-30 Original Indicative 0
USD
2020-09-01 2020-09-30 Revised Indicative 4,890,833.33
USD
2020-10-01 2020-10-31 Original Indicative 0
USD
2020-10-01 2020-10-31 Revised Indicative 4,890,833.33
USD
2020-11-01 2020-11-30 Original Indicative 0
USD
2020-11-01 2020-11-30 Revised Indicative 4,890,833.33
USD
2020-12-01 2020-12-31 Original Indicative 0
USD
2020-12-01 2020-12-31 Revised Indicative 4,890,833.33
USD
2021-01-01 2021-01-31 Original Indicative 0
USD
2021-01-01 2021-01-31 Revised Indicative 4,890,833.33
USD
2021-02-01 2021-02-28 Original Indicative 0
USD
2021-02-01 2021-02-28 Revised Indicative 4,890,833.33
USD
2021-03-01 2021-03-31 Original Indicative 0
USD
2021-03-01 2021-03-31 Revised Indicative 4,890,833.33
USD
2021-04-01 2021-04-30 Original Indicative 0
USD
2021-04-01 2021-04-30 Revised Indicative 4,890,833.33
USD
2021-05-01 2021-05-31 Original Indicative 0
USD
2021-05-01 2021-05-31 Revised Indicative 4,890,833.33
USD
2021-06-01 2021-06-30 Original Indicative 0
USD
2021-06-01 2021-06-30 Revised Indicative 4,890,833.37
USD
Budget
Transactions ( 78 )
Outgoing Commitment ( 3 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2013-06-30
Total Commitment in June Month of 2013
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
236,000,000
USD
2020-06-30
Total Commitment Cancellations in June Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-13,121,797
USD
2021-01-31
Total Commitment Cancellations in January Month of 2021
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-49,622,420
USD
Outgoing Commitment
Disbursement ( 40 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2014-03-31
Total Disbursement in March Month of 2014
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
48,673,453
USD
2014-04-30
Total Disbursement in April Month of 2014
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
5,487,995
USD
2014-06-30
Total Disbursement in June Month of 2014
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
14,624
USD
2014-08-31
Total Disbursement in August Month of 2014
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
11,724,758
USD
2014-10-31
Total Disbursement in October Month of 2014
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,125,764
USD
2014-12-31
Total Disbursement in December Month of 2014
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
3,142,573
USD
2015-03-31
Total Disbursement in March Month of 2015
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
5,822,321
USD
2015-04-30
Total Disbursement in April Month of 2015
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,995,875
USD
2015-07-31
Total Disbursement in July Month of 2015
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
3,723,726
USD
2015-08-31
Total Disbursement in August Month of 2015
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,925,846
USD
2015-12-31
Total Disbursement in December Month of 2015
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
3,209,734
USD
2016-02-29
Total Disbursement in February Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
3,533,957
USD
2016-07-31
Total Disbursement in July Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
5,497,550
USD
2016-08-31
Total Disbursement in August Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
35,092
USD
2016-09-30
Total Disbursement in September Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
671,128
USD
2016-11-30
Total Disbursement in November Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,326,852
USD
2016-12-31
Total Disbursement in December Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
497,987
USD
2017-01-31
Total Disbursement in January Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
46,553
USD
2017-04-30
Total Disbursement in April Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,491,692
USD
2017-06-30
Total Disbursement in June Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
7,553,943
USD
2017-08-31
Total Disbursement in August Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
244,652
USD
2017-10-31
Total Disbursement in October Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,901,561
USD
2018-01-31
Total Disbursement in January Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
75,310
USD
2018-02-28
Total Disbursement in February Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,220,931
USD
2018-03-31
Total Disbursement in March Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
3,052,374
USD
2018-06-30
Total Disbursement in June Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
3,698,381
USD
2018-07-31
Total Disbursement in July Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
4,440,725
USD
2018-08-31
Total Disbursement in August Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
135,848
USD
2018-12-31
Total Disbursement in December Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,652,990
USD
2019-01-31
Total Disbursement in January Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,056,996
USD
2019-03-31
Total Disbursement in March Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,997,851
USD
2019-06-30
Total Disbursement in June Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
6,003,810
USD
2019-08-31
Total Disbursement in August Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
714,680
USD
2019-11-30
Total Disbursement in November Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
727,555
USD
2019-12-31
Total Disbursement in December Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,384,067
USD
2020-03-31
Total Disbursement in March Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
8,505,280
USD
2020-06-30
Total Disbursement in June Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
2,749,358
USD
2020-11-30
Total Disbursement in November Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
1,408,576
USD
2020-12-31
Total Disbursement in December Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
8,553,380
USD
2021-01-31
Total Disbursement in January Month of 2021
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-576,353
USD
Disbursement
Interest Payment ( 22 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2014-06-30
Total Interest Repayment in June Month of 2014
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-276,314
USD
2014-12-31
Total Interest Repayment in December Month of 2014
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-587,340
USD
2015-06-30
Total Interest Repayment in June Month of 2015
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-654,918
USD
2015-12-31
Total Interest Repayment in December Month of 2015
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-788,209
USD
2016-06-30
Total Interest Repayment in June Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-840,073
USD
2016-12-31
Total Interest Repayment in December Month of 2016
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-864,384
USD
2017-06-30
Total Interest Repayment in June Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-923,269
USD
2017-12-31
Total Interest Repayment in December Month of 2017
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,077,868
USD
2018-06-30
Total Interest Repayment in June Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,105,885
USD
2018-12-31
Total Interest Repayment in December Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,173,182
USD
2019-06-30
Total Interest Repayment in June Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,160,253
USD
2019-12-31
Total Interest Repayment in December Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,093,285
USD
2020-06-30
Total Interest Repayment in June Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,174,607
USD
2020-12-31
Total Interest Repayment in December Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,216,549
USD
2021-06-30
Total Interest Repayment in June Month of 2021
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,342,818
USD
2021-12-31
Total Interest Repayment in December Month of 2021
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,251,482
USD
2022-06-30
Total Interest Repayment in June Month of 2022
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,144,160
USD
2022-12-31
Total Interest Repayment in December Month of 2022
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-886,416
USD
2023-06-30
Total Interest Repayment in June Month of 2023
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,311,733
USD
2023-12-31
Total Interest Repayment in December Month of 2023
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-904,994
USD
2024-06-30
Total Interest Repayment in June Month of 2024
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-1,095,365
USD
2024-12-31
Total Interest Repayment in December Month of 2024
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-927,281
USD
Interest Payment
Loan Repayment ( 13 )
DATE DESCRIPTION PROVIDER RECEIVER VALUE
2018-12-31
Total Loan Repayment in December Month of 2018
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-7,117,243
USD
2019-06-30
Total Loan Repayment in June Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-7,139,643
USD
2019-12-31
Total Loan Repayment in December Month of 2019
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-7,143,565
USD
2020-06-30
Total Loan Repayment in June Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-7,119,101
USD
2020-12-31
Total Loan Repayment in December Month of 2020
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-3,450,623
USD
2021-06-30
Total Loan Repayment in June Month of 2021
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-2,492,404
USD
2021-12-31
Total Loan Repayment in December Month of 2021
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-2,418,576
USD
2022-06-30
Total Loan Repayment in June Month of 2022
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-2,306,492
USD
2022-12-31
Total Loan Repayment in December Month of 2022
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-4,609,486
USD
2023-06-30
Total Loan Repayment in June Month of 2023
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-4,622,717
USD
2023-12-31
Total Loan Repayment in December Month of 2023
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-4,644,053
USD
2024-06-30
Total Loan Repayment in June Month of 2024
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-4,563,800
USD
2024-12-31
Total Loan Repayment in December Month of 2024
FLOW ODA 10
FINANCE Aid loan excluding debt reorganisation Withdrawn 410
IDA Credit
REF 44002
-4,540,870
USD
Loan Repayment
General Enquiries
The World Bank
Anup Karanth
+1-202-473-1000
The World Bank, 1818 H Street, NW, Washington, DC 20433 USA
conditions( 13 )
NARRATIVE TYPE DESCRIPTION
Finance Agreement :Anti-Corruption | Description :Recipient to ensure that project is carried in accordance with the provisions ofAnti-Corruption Guidelines. | Frequency :CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Contingent Emergency Response Mechanism | Description :GoPY and GoTN to prepare a CER OM, nominate and maintaina coordination authority for purpose (and prior to) the implementation of the CER components under their respective Parts of theProjectGoPY and GoTN have (i) determined that an eligible crisis and emergency has occurred and devised activities in responsethereof, and (ii) submitted said activities for the Association concurrence | Frequency :CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Fisheries Livelihoods Support | Description :GoTN to prepare and adopt some guidelines and selection criteriafor the determination of eligible beneficiaries for the distribution provision of in-kind grants (low-cost communication equipment)| Due Date :01-Jul-2015
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Institutional Arrangements – Consultancy Contracts and MOU | Description :• GoPY to select a Project ManagementConsultant to assist the PIA with project implementation. GoPY to maintain a firm of chartered accountants in order to carry outtheannual Financial Statements for the Project GoTN to maintain the firm of chartered accountants in order to carry outsemi-annual internal audits and the assessment of the internal control protocols. | Due Date :31-Mar-2014
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Institutional Arrangements – Implementation Units | Description :GoPY to maintain a Governing Body of PIA(former empowered committee), the PIA, and an implementation unit in the PWD for purposes of implementing the Project. GoTN tomaintain a state level Steering Committee, an Empowered Committee, a Project Management Unit (within OCRA) and projectimplementation units in the line agencies and departments (RD&PRD, PWD, DOF, TANGEDCO, SMA and DOEF) | Frequency :CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Management Information System for GoPY | Description :GoPY to establish a similar mechanism (includingprocurement modules) | Due Date :28-Feb-2014
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Management Information System for GoTN | Description :GoTN to maintain a MIS and update it with a procurementmodule including a grievance complaint mechanism and procurement documentation, record keeping systems including disclosure in afree website. | Due Date :28-Feb-2014
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Project Documents | Description :GoPY to implement its respective Part of the Project in accordance with its OM,Guidelines for the Selection of Beneficiaries, and the safeguard documents (ESMF, EMPs and RAPs –if applicable).GoTN to implementits respective Part of the Project in accordance with the OM, the Guidelines for the Selection of Beneficiaries, constructionguidelines and the safeguard documents | Frequency :CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Resilient Electrical Network | Description :GoTN to enter into a written agreement with TANGECDO for theimplementation of the resilient electrical network components (underground cable installation) under terms and conditionsacceptable to the Association | Due Date :30-Jun-2014
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Resilient Housing | Description :GoTN shall get reimbursed relocation support expenditures in respect of housesthat have been substantially completed and handed over to the respective owner. | Frequency :CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Safeguards 1 | Description :GoPY and GoTN to carry out the Project in accordance with the respective ESMF andEMPs. GoPY and GoTN shall invite bids for civil works once the environmental and social assessment of such works have been carriedout in accordance with the respective ESMF | Frequency :CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Safeguards 2 | Description :No works shall commence until all necessary government permits and clearance shallhave been obtained, and any conditions therefor have been complied withGoPY and GoTN to maintain monitoring and evaluationprotocols to assess compliance with the safeguard documents/requirements, and produce quarterly reports | Frequency :CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient
Finance Agreement :Safeguards 3 | Description :GoPY and GoTN to finance any compensation for resettlement and/or rehabilitation outof its own resources | Frequency :CONTINUOUS
Performance The condition attached requires certain outputs or outcomes to be achieved by the recipient